Renewable sitesKingspan

Kingspan

Kingspan is an operational 1.8 MW onshore wind farm in Flintshire, generating since 11 January 2019. Planning permission was granted on 14 April 2015, 5 months after submission. Operator of record: Kingspan.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 11 January 2019
Wind Onshore
Technology
Kingspan
Flintshire
Authority
Wales

Planning and build timeline

Application submitted19 November 2014
Permission granted14 April 2015
5 months after submission
Operational11 January 2019
45 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Flintshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kingspan’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
25.6 km
Solar Photovoltaics · Operational
1.211.2 km
Solar Photovoltaics · Operational
1.612.5 km
EfW Incineration · Operational
1612.6 km
Solar Photovoltaics · Operational
72.213.1 km
Solar Photovoltaics · Operational
3.813.6 km

How big is Kingspan?

Kingspan has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kingspan?

REPD records the operator as Kingspan. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kingspan approved and built?

The application was submitted on 19 November 2014. Permission was granted on 14 April 2015, 5 months later. The site became operational on 11 January 2019, 45 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4790.