Crumps Yard Solar Farm
Crumps Yard Solar Farm is an operational 1.6 MW solar farm in Flintshire, generating since 1 February 2021. Planning permission was granted on 23 September 2020, 9 months after submission. Operator of record: Flintshire County Council.
Planning and build timeline
| Application submitted | 10 December 2019 |
| Permission granted | 23 September 2020 9 months after submission |
| Operational | 1 February 2021 4 months after consent |
Screening a site of your own?
Flintshire approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Crumps Yard Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
Flintshire’s record on solar
Flintshire has decided 11 solar farms and approved 82%, taking a median of 6.4 months. See every solar farm decision in Flintshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 3.8 | 2.2 km |
EfW Incineration · Operational | 16 | 2.3 km |
Solar Photovoltaics · Operational | 72.2 | 3.2 km |
Solar Photovoltaics · Operational | 2 | 7 km |
Solar Photovoltaics · Operational | 1.2 | 7.9 km |
Battery · Operational | 100 | 7.9 km |
Battery · Under Construction | 57 | 8.8 km |
Battery · Operational | 57 | 8.8 km |
How big is Crumps Yard Solar Farm?
Crumps Yard Solar Farm has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crumps Yard Solar Farm?
REPD records the operator as Flintshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crumps Yard Solar Farm approved and built?
The application was submitted on 10 December 2019. Permission was granted on 23 September 2020, 9 months later. The site became operational on 1 February 2021, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7834.