Renewable sites › East Youlstone Wind Farm
East Youlstone Wind Farm
East Youlstone Wind Farm is operational in Torridge with a recorded capacity of 4 MW, and has been generating since 2015-02-15.
Planning and build timeline
| Application submitted | 2011-04-04 |
| Permission granted | 2012-11-09 19 months after submission |
| Operational | 2015-02-15 27 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on onshore wind
Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chester Energy (East Woolley Farm) Solar Photovoltaics · Operational | 5 | 2.9 km |
Crimp Wind Farm Wind Onshore · Operational | 2.4 | 3 km |
East Langford Farm Solar Photovoltaics · Operational | 5 | 5.4 km |
Walland Farm Solar Photovoltaics · Operational | 5 | 9.6 km |
Limebury Farm, Horns Cross - Solar Farm Solar Photovoltaics · Under Construction | 6.5 | 10.4 km |
Pitworthy Farm Solar Park Solar Photovoltaics · Operational | 15.6 | 10.8 km |
North Tamar Environ Project - Holsworthy (Farm AD) Anaerobic Digestion · Operational | 1.4 | 12 km |
Galsworthy Wind Park Wind Onshore · Operational | 9.2 | 12.3 km |
How big is East Youlstone Wind Farm?
East Youlstone Wind Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates East Youlstone Wind Farm?
REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was East Youlstone Wind Farm approved and built?
The application was submitted on 2011-04-04. Permission was granted on 2012-11-09, 19 months later. The site became operational on 2015-02-15, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4168.