Planning and build timeline
| Application submitted | 1998-12-21 |
| Permission granted | 1999-05-14 5 months after submission |
| Operational | 2002-07-18 38 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Derriton Fields Solar Farm Solar Photovoltaics · Operational | 11.8 | 3 km |
Great Knowle Farm Solar Solar Photovoltaics · Operational | 3 | 3.2 km |
Foxcombe Farm Solar Park Solar Photovoltaics · Operational | 5 | 5 km |
Pitworthy Farm Solar Park Solar Photovoltaics · Operational | 15.6 | 5.4 km |
Land West of Parsonage Wood Solar Photovoltaics · Operational | 4.2 | 5.4 km |
CRINACOTT SOLAR FARM (Pyworthy) Solar Photovoltaics · Operational | 6.7 | 5.4 km |
EASTACOMBE SOLAR FARM Solar Photovoltaics · Operational | 3.6 | 6.2 km |
Derril Water Solar Farm - Solar Farm Solar Photovoltaics · Operational | 42 | 6.3 km |
How big is North Tamar Environ Project - Holsworthy (Farm AD)?
North Tamar Environ Project - Holsworthy (Farm AD) has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North Tamar Environ Project - Holsworthy (Farm AD)?
REPD records the operator as Holsworthy Biogas Company ( North Tamar Business Network). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North Tamar Environ Project - Holsworthy (Farm AD) approved and built?
The application was submitted on 1998-12-21. Permission was granted on 1999-05-14, 5 months later. The site became operational on 2002-07-18, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 209.