Renewable sitesGalsworthy Wind Park

Galsworthy Wind Park

Galsworthy Wind Park is an operational 9.2 MW onshore wind farm in Torridge, generating since 28 November 2014. Planning permission was granted on 11 September 2008, 5 months after submission. Operator of record: Ecotricity.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 28 November 2014
Wind Onshore
Technology
Ecotricity
Torridge
Authority
England

Planning and build timeline

Application submitted4 April 2008
Permission granted11 September 2008
5 months after submission
Operational28 November 2014
75 months after consent

Screening a site of your own?

RedlineUK · £39

Torridge approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Galsworthy Wind Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on onshore wind

Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.25.4 km
Solar Photovoltaics · Under Construction
6.57.6 km
Solar Photovoltaics · Operational
58.3 km
Solar Photovoltaics · Operational
3.311.3 km
Anaerobic Digestion · Operational
1.411.6 km
Solar Photovoltaics · Operational
0.1511.7 km
Solar Photovoltaics · Operational
512.2 km
Wind Onshore · Operational
2.612.2 km

How big is Galsworthy Wind Park?

Galsworthy Wind Park has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Galsworthy Wind Park?

REPD records the operator as Ecotricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Galsworthy Wind Park approved and built?

The application was submitted on 4 April 2008. Permission was granted on 11 September 2008, 5 months later. The site became operational on 28 November 2014, 75 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4624.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode