Novarly ParcelRenewable planning

Renewable planning Onshore windTorridge

Onshore wind planning in Torridge

Torridge has decided 8 onshore wind schemes and approved 63% of them, taking a median of 18.3 months to decide. Consented capacity: 25 MW. 2 applications still awaiting a decision.

63%
Approved
5 granted · 3 refused
18.3 mo
Median decision
UK 11.5 mo
25 MW
Consented
25 MW refused
3
Appeals
3 allowed on appeal

How Torridge compares

Against the 75 UK authorities with 5+ onshore wind decisions, Torridge sits in the 36th percentile for approval rate (5 points below the England average) and the 24th percentile for speed.

Decisions by year

35Approved — 1 (2012)Refused — 1 (2012)212Approved — 1 (2013)113Approved — 1 (2014)Refused — 1 (2014)214Refused — 1 (2015)115
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (13)

SchemeMWStatusDecided
Tatson Farm - Wind Turbine
Constantine Wind Energy Limited · 1/0170/2025/FUL
Application Submitted2025-03-17
North Devon Wind Farm
North Devon Wind Energy Ltd · 1/0288/2013/FULM · 21.8 mo to decide
7.5Application Refused2015-02-02
Harbourcross wind farm
Harbourcross Wind Farm Ltd · 1/0412/2013/FULM · 17.3 mo to decide
10Application Refused2014-10-31
Hollow Panson Wind Farm
EDF Energy Renewables · 1/1171/2012/FULM
12Application Withdrawn2014-08-07
Nethercott Farm
Private Developer · 1/0036/2014/FULM · 5.6 mo to decide
1.5Operational2014-07-03
Harbourcross Wind Farm
Wind Ventures · 1/0506/2012/FULM
15Revised2013-04-26
Dunsland Cross Wind Farm
Temporis Capital · 1/1250/2011/FULM · 12.3 mo to decide
7.5Operational2013-01-22
Wheelers Cross
Wind Prospect · 1/0336/2011/FULM · 20 mo to decide
7.8Application Refused2012-12-07
East Youlstone Wind Farm
Airvolution Energy · 1/0311/2011/FULM · 19.2 mo to decide
4Operational2012-11-09
Galsworthy Wind Park
Ecotricity · 1/0375/2008/FUL · 5.3 mo to decide
9.2Operational2008-09-11
Sedborough Farm
Parkham Farms and Power Ltd
2Application Withdrawn2008-05-13
Cairn Brae Wind Turbine
Private Developer · 1/1683/2002
1.3Application Withdrawn2004-12-02
Darracott Moor
Gresham House · 1/1345/2002/24 · 21.8 mo to decide
2.6Operational2004-05-13

Does Torridge approve onshore wind schemes?

Yes — of the 8 onshore wind schemes Torridge has decided, 63% were approved (5 granted, 3 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Torridge?

The median time from application to decision is 18.3 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Torridge consented?

25 MW has been consented across 5 approved schemes, with 25 MW refused. A further 2 applications awaits a decision.

Other technologies in Torridge

Solar in TorridgeBattery storage in Torridge

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.