Chester Energy (East Woolley Farm) is an operational 5 MW solar farm in Cornwall, generating since 1 June 2012. Planning permission was granted on 18 April 2011, 4 months after submission. Operator of record: Chester Energy (Eastcott).
Planning and build timeline
| Application submitted | 17 December 2010 |
| Permission granted | 18 April 2011 4 months after submission |
| Operational | 1 June 2012 13 months after consent |
Screening a site of your own?
Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Chester Energy (East Woolley Farm)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on solar
Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.4 | 1.3 km |
Wind Onshore · Operational | 4 | 2.9 km |
Solar Photovoltaics · Operational | 5 | 7.3 km |
Solar Photovoltaics · Operational | 5 | 11.4 km |
Solar Photovoltaics · Operational | 15.6 | 12.1 km |
Solar Photovoltaics · Under Construction | 6.5 | 12.3 km |
Anaerobic Digestion · Operational | 1.4 | 14.2 km |
Solar Photovoltaics · Operational | 1.8 | 14.8 km |
How big is Chester Energy (East Woolley Farm)?
Chester Energy (East Woolley Farm) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chester Energy (East Woolley Farm)?
REPD records the operator as Chester Energy (Eastcott). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chester Energy (East Woolley Farm) approved and built?
The application was submitted on 17 December 2010. Permission was granted on 18 April 2011, 4 months later. The site became operational on 1 June 2012, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1024.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode