Renewable sites › Crimp Wind Farm
Crimp Wind Farm
Crimp Wind Farm is operational in Cornwall with a recorded capacity of 2.4 MW, and has been generating since 2011-04-01.
Planning and build timeline
| Application submitted | 2004-12-13 |
| Permission granted | 2008-04-02 40 months after submission |
| Operational | 2011-04-01 36 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on onshore wind
Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chester Energy (East Woolley Farm) Solar Photovoltaics · Operational | 5 | 1.3 km |
East Youlstone Wind Farm Wind Onshore · Operational | 4 | 3 km |
East Langford Farm Solar Photovoltaics · Operational | 5 | 6.3 km |
Pitworthy Farm Solar Park Solar Photovoltaics · Operational | 15.6 | 10.9 km |
Walland Farm Solar Photovoltaics · Operational | 5 | 12.2 km |
Limebury Farm, Horns Cross - Solar Farm Solar Photovoltaics · Under Construction | 6.5 | 13.1 km |
North Tamar Environ Project - Holsworthy (Farm AD) Anaerobic Digestion · Operational | 1.4 | 13.4 km |
Creathorne Farm - Solar Farm Solar Photovoltaics · Operational | 1.8 | 13.5 km |
How big is Crimp Wind Farm?
Crimp Wind Farm has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crimp Wind Farm?
REPD records the operator as Crimp Power Ltd (West Coast Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crimp Wind Farm approved and built?
The application was submitted on 2004-12-13. Permission was granted on 2008-04-02, 40 months later. The site became operational on 2011-04-01, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3458.