Onshore wind planning in North Lanarkshire

North Lanarkshire has decided 20 onshore wind schemes and approved 70% of them, taking a median of 16.8 months to decide. Consented capacity: 143 MW. 6 applications still awaiting a decision.

70%
Approved
14 granted · 6 refused
16.8 mo
Median decision
UK 11.5 mo
143 MW
Consented
96 MW refused
4
Appeals
2 allowed on appeal

How North Lanarkshire compares

Against the 75 UK authorities with 5+ onshore wind decisions, North Lanarkshire sits in the 54th percentile for approval rate (2 points above the England average) and the 28th percentile for speed.

Decisions by year

35Approved — 1 (2010)110Approved — 1 (2011)111Approved — 1 (2012)Refused — 1 (2012)212Refused — 2 (2013)213Refused — 2 (2014)214Approved — 2 (2015)215Approved — 1 (2017)117Approved — 2 (2019)219Approved — 2 (2020)220Approved — 1 (2024)124Approved — 1 (2025)Refused — 1 (2025)225
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (30)

SchemeMWStatusDecided
A Bartlett and Sons - Wind turbine
Albert Bartlett & Sons (Airdrie) Limited · 23/01203/FUL · 20.1 mo to decide
1Awaiting Construction2025-07-25
Torrance Wind Farm Extension 2
Infinergy · 23/00256/FUL · 23.3 mo to decide
26.4Application Refused2025-03-07
Dewshill Wind Farm
Wind Estate (UK) Ltd · 23/00379/FUL · 13.8 mo to decide
9Awaiting Construction2024-06-19
Forrest Road, Salsburgh - 2 Wind Turbines
Wind Estate (UK) Ltd · 23/00379/FUL
Application Submitted2023-04-26
Forrest Road, Salsburgh - Wind Farm
Wind Estate (UK) Ltd · 22/00324/FUL
12.6Revised2022-03-18
Brownhill Farm
Wind Estate · 20/00504/FUL · 2.2 mo to decide
8.4Under Construction2020-07-17
Watsonhead Wind Farm
Green Cat Renewables · 24.1 mo to decide
8.4Operational2020-02-24
Southrigg 2
SR Wind Limited · 19/00644/FUL · 2.1 mo to decide
4.2Awaiting Construction2019-07-31
Greengairs East Wind Farm
Muirhall Energy · 12/00602/FUL · 79.5 mo to decide
24Operational2019-02-13
Brownhill Farm
Wind Estate · 18/01433/FUL
8.4Revised2018-11-05
Hartwood Windfarm
ABO Wind UK · 14/01699/FUL · 39 mo to decide
21Planning Permission Expired2017-11-24
Southrigg 2
Rigg Wind · 17/01478/FUL
1.5Revised2017-09-04
West Benhar wind farm
EDF Energy Renewables · 13/01377/FUL · 25.6 mo to decide
27.2Operational2015-09-11
Southrigg
Southrigg WT · 14/02112/FUL · 9.2 mo to decide
1.5Operational2015-08-12
Forrestfield Wind Farm
West Cost Energy · 15/01411/FUL
13.2Application Submitted2015-07-02
Land South East Of Auchterhead
1 Stop Renewables · 15/00395/FUL
2.3Application Submitted2015-03-03
Starryshaw Wind Farm
WilloWind Energy Ltd · 13/00669/FUL · 20 mo to decide
12Application Refused2014-12-24
Shotts wind farm
Airvolution Energy · 13/00072/FUL · 15.4 mo to decide
18Appeal Refused2014-05-23
Benhar Windfarm
Eneco · 13/00501/FUL · 7.9 mo to decide
15Appeal Refused2013-11-25
Hartwood
Red Group · 06/01001/FUL
30Application Withdrawn2013-09-06
Damside Wind Farm
Damside Wind Farm Ltd · 12/00808/FUL · 7.6 mo to decide
20Application Refused2013-03-07
Birniehill
Scottish and Southern Energy (SSE) · 07/01341/FUL · 62.7 mo to decide
4.5Application Refused2012-10-09
Torrance Farm Wind Park Extension
Capital Dynamics · 12/00284/FUL · 4.4 mo to decide
5.7Operational2012-07-31
Nether braco Farm
Airtricity Developments · C/08/00462/FUL
21Application Withdrawn2011-10-27
West Torrance Farm
WRS West Torrance · 11/00575/FUL
1.5Application Withdrawn2011-06-28
Torrance Farm
Future Spectrum Ltd · 10/00973/FUL · 5.8 mo to decide
9Operational2011-02-24
Damhead Farm
Private Developer · 07/00809/FUL · 32.2 mo to decide
2.5Operational2010-01-14
Salsburgh
Salsburgh Windco Ltd · 05/00132/FUL
24Application Withdrawn2009-07-24
Greengairs Wind Farm
Muirhall Energy (formerly Infinis) · 07/00172/FUL · 18.2 mo to decide
17.5Planning Permission Expired2008-08-14
Greendykeside
A7 Energy · 04/01624/FUL · 7.9 mo to decide
4Operational2005-05-11

Does North Lanarkshire approve onshore wind schemes?

Yes — of the 20 onshore wind schemes North Lanarkshire has decided, 70% were approved (14 granted, 6 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in North Lanarkshire?

The median time from application to decision is 16.8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has North Lanarkshire consented?

143 MW has been consented across 14 approved schemes, with 96 MW refused. A further 6 applications awaits a decision.

Other technologies in North Lanarkshire

Solar in North LanarkshireBattery storage in North Lanarkshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.