Novarly ParcelRenewable sites

Renewable sitesGreengairs Landfill Scheme Phase IV

Greengairs Landfill Scheme Phase IV

Greengairs Landfill Scheme Phase IV is an operational 2 MW landfill gas site in North Lanarkshire, generating since 13 August 1999. Planning permission was granted on 12 September 1997, 3 months after submission. Operator of record: Waste Recycling Group.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 13 August 1999
Landfill Gas
Technology
Waste Recycling Group
North Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted24 June 1997
Permission granted12 September 1997
3 months after submission
Operational13 August 1999
23 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in North Lanarkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Greengairs Landfill Scheme Phase IV’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
40 km
Landfill Gas · Operational
1.90 km
Landfill Gas · Operational
2.20 km
Landfill Gas · Operational
2.20 km
Landfill Gas · Operational
20 km
Wind Onshore · Operational
242.1 km
Wind Onshore · Operational
42.7 km
Wind Onshore · Operational
2.55.7 km

How big is Greengairs Landfill Scheme Phase IV?

Greengairs Landfill Scheme Phase IV has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Greengairs Landfill Scheme Phase IV?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Greengairs Landfill Scheme Phase IV approved and built?

The application was submitted on 24 June 1997. Permission was granted on 12 September 1997, 3 months later. The site became operational on 13 August 1999, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 693.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode