Greengairs East Wind Farm
Greengairs East Wind Farm is an operational 24 MW onshore wind farm in North Lanarkshire, generating since 25 August 2023. Planning permission was granted on 13 February 2019, 80 months after submission. Operator of record: Muirhall Energy.
Planning and build timeline
| Application submitted | 29 June 2012 |
| Permission granted | 13 February 2019 80 months after submission |
| Operational | 25 August 2023 54 months after consent |
Screening a site of your own?
North Lanarkshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Greengairs East Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
North Lanarkshire’s record on onshore wind
North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4 | 1.3 km |
Landfill Gas · Operational | 2 | 2.1 km |
Landfill Gas · Operational | 2.2 | 2.1 km |
Landfill Gas · Operational | 1.9 | 2.1 km |
Landfill Gas · Operational | 2.2 | 2.1 km |
Landfill Gas · Operational | 4 | 2.1 km |
Landfill Gas · Operational | 2 | 2.1 km |
Wind Onshore · Operational | 2.5 | 5.4 km |
How big is Greengairs East Wind Farm?
Greengairs East Wind Farm has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Greengairs East Wind Farm?
REPD records the operator as Muirhall Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Greengairs East Wind Farm approved and built?
The application was submitted on 29 June 2012. Permission was granted on 13 February 2019, 80 months later. The site became operational on 25 August 2023, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4213.