Onshore wind planning in Cornwall

Cornwall has decided 35 onshore wind schemes and approved 74% of them, taking a median of 7.5 months to decide. Consented capacity: 143 MW. 14 applications still awaiting a decision.

74%
Approved
26 granted · 9 refused
7.5 mo
Median decision
UK 11.5 mo
143 MW
Consented
79 MW refused
10
Appeals
3 allowed on appeal

How Cornwall compares

Against the 75 UK authorities with 5+ onshore wind decisions, Cornwall sits in the 61st percentile for approval rate (6 points above the England average) and the 88th percentile for speed.

Decisions by year

35Approved — 1 (2010)110Refused — 2 (2011)211Approved — 1 (2012)Refused — 1 (2012)212Approved — 4 (2013)413Refused — 1 (2014)114Refused — 1 (2015)115Refused — 2 (2016)216Approved — 2 (2019)219Approved — 1 (2021)121Approved — 1 (2022)122Approved — 2 (2024)224Approved — 2 (2025)225
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (54)

SchemeMWStatusDecided
Dubbers China Clay Works, Nanpean - Wind Turbines
Clean Earth Energy Limited · PA25/09509
Application Submitted2026-02-16
Higher Biscovillack Farm, Greensplat - Wind Turbine
Clean Earth Energy Limited · PA25/09581
4.3Application Submitted2026-01-21
Lidcott, Laneast - Wind Turbine
Devon & Cornwall Logs Limited · PA25/08501
1Application Submitted2025-11-11
Brew Farm, St Levan - Wind Turbine
Re Wind Green Projects Limited · PA25/07818
0.23Application Submitted2025-10-28
Treliever Cross Research Fields, Longdowns - Wind Turbine
University of Exeter · PA24/09072 · 7.4 mo to decide
1Awaiting Construction2025-07-18
Burngullow Common - Wind Turbine
Clean Earth Energy Limited · PA23/09937 · 12.6 mo to decide
4.1Awaiting Construction2025-01-24
Helsbury Park Woods, Michaelstow - Wind Turbine
Octopus Energy · PA24/06612
0.9Application Submitted2024-09-12
Callywith Quarry, Roselands Lane - Wind Turbine
Constantine Wind Energy Limited · PA23/08661 · 5.4 mo to decide
0.23Awaiting Construction2024-07-12
Goonamarth Farm - Wind Turbine
Clean Earth Energy Limited · PA23/10069 · 3.2 mo to decide
4.3Under Construction2024-05-01
Bears Down Wind Farm
Clean Earth Energy Limited · PA23/10324
22.5Application Submitted2024-02-01
Cold Northcott Windfarm Repowering
RMA Environmental Limited · PA23/02727
22Application Submitted2023-11-27
Wheal Martyn, Carthew - 1 Wind turbine
Clean Earth Energy / Imerys Minerals Limited · PA21/07216 · 7.2 mo to decide
1.3Awaiting Construction2022-02-17
Lower Longstones, St Mewan Wind Turbine
Clean Earth Energy Limited · PA20/09318 · 3.4 mo to decide
4.1Awaiting Construction2021-03-01
Land near Ventonteague
Cornwall Council · PA18/08772 · 13.7 mo to decide
2.3Operational2019-12-01
Lower Tregeen, Davidstow - Wind Turbine
Powerquinn Limited · PA18/10990 · 3.4 mo to decide
0.9Under Construction2019-03-05
Scarcewater Tip
REG Windpower · PA15/00511 · 13.8 mo to decide
6.9Appeal Refused2016-03-17
Land At Pines Tip
REG Windpower · PA15/00955 · 13.4 mo to decide
2.7Appeal Refused2016-03-15
Land near Ventonteague
Cornwall Council · PA15/02972 · 7 mo to decide
1.5Revised2015-10-26
Scotland Corner wind farm
Coriolis Energy · PA14/08635 · 6.5 mo to decide
15Application Refused2015-04-10
Big Field Wind Farm
Good Energy · PA14/02107 · 7.8 mo to decide
25.3Appeal Refused2014-10-28
Davidstow Wind Farm
Community Windpower · PA13/03743
48Application Withdrawn2014-01-29
Denzell Downs Wind Farm
REG Windpower / BlackRock · PA13/04805 · 5.5 mo to decide
10Operational2013-12-12
Goonabarn Farm Wind Turbines
George Richards Farms Partnership · PA13/00848 · 4.7 mo to decide
1Operational2013-07-04
Mendennick Wind Farm
REG Windpower · PA12/12027
2.6Application Withdrawn2013-04-10
Woodlands Barton Wind Project
Private Developer · PA12/10296 · 2.9 mo to decide
4.6Operational2013-02-11
Garlenick Estate 2 - Wind Turbines
Airvolution Energy · PA12/09852 · 3 mo to decide
4Operational2013-01-31
Wheal Jane Sustainability Wind Farm
Partnerships for Renewables · PA11/08372 · 12.1 mo to decide
2Appeal Refused2012-10-16
St. Breock Re-Power
REG & Blackrock · PA12/02907 · 6.4 mo to decide
10Operational2012-10-03
Denzell Downs
REG Windpower · PA11/01429 · 7.1 mo to decide
10Revised2011-10-03
Truthan Barton Wind Farm
Coronation Power · PA11/03197 · 4.9 mo to decide
12.5Appeal Refused2011-09-28
Treworgans Wind Turbine
Private Developer · NR/10/00063/WIND · 17.5 mo to decide
2Appeal Refused2011-08-19
Crimp Wind Farm
Crimp Wind farm · 2008/02196
2.4Revised2011-05-05
Truthan Barton Wind Farm
Coronation Power · C1/EA30/0377/09/M · 22.4 mo to decide
17.5Revised2011-01-20
Bodmin Moor
Community Power Ltd · E1/2008/01432 · 24.2 mo to decide
50Appeal Withdrawn2010-07-26
Carland Cross Wind Farm Repowering
Scottish Power Renewables · EA28/2038/08/B · 13.9 mo to decide
20Operational2010-01-20
Delabole (Repowering)
Good Energy Generation · 20.2 mo to decide
9.2Operational2009-12-12
Otterham Down Wind Farm
Otter Power · 2006/01274 · 39.8 mo to decide
3.2Operational2009-10-13
Hendraburnick
Ecotricity · 2007/01497
8Application Withdrawn2009-07-07
Eden Project
The Eden Project · 08/01411
2Application Withdrawn2009-05-20
Carn Vean
Unknown · PA08/01190/F · 2.5 mo to decide
10Operational2008-09-11
Goonhilly Downs Wind Farm Repower
REG Windpower (previously Cornwall Light & Power) · PA07/02103/FM · 7.5 mo to decide
12Operational2008-08-04
Crimp Wind Farm
Crimp Power Ltd (West Coast Energy) · 2004/02831 · 39.6 mo to decide
2.4Operational2008-04-02
Delabole Wind Farm
Wind Electric
4Decommissioned2008-04-02
Penpell Wind Cluster
Private Developer · 301146 · 21.6 mo to decide
2.6Application Refused2005-04-01
Davidstow Wind Farm
RWE npower
7.8Revised2005-02-16
Roskrow Wind Turbines
REG Windpower (previously Cornwall Light and Power) · PA02/01417 · 14.8 mo to decide
1.7Operational2004-02-25
St. Breock Re-Power
Renewable Energy Generation Limited - previously E.on · 2002-1897 · 7.5 mo to decide
10.4Revised2003-01-30
Otterham Down Wind Farm
Otterham Wind Farm Ltd - Powergen Renewables · 2002/0998 · 8.1 mo to decide
7.4Revised2003-01-21
Bears Down Wind Farm
Natural Power · 1.4 mo to decide
9.8Operational2000-06-27
Worthy Vale Manor
Worthyvale Manor Partnership · 31.6 mo to decide
10.1Application Refused1996-06-28
Four Burrows Wind Farm
Renewable Energy Systems (RES) · PA14/1456/94 · 3.5 mo to decide
4.5Operational1995-03-09
Carland Cross
Scottish Power Renewables · 11 mo to decide
6Decommissioned1992-04-29
Cold Northcott
Otter Power
6.6Operational
Goonhilly Downs - Wind
REG Windpower (previously Cornwall Light and Power)
5.6Decommissioned

Does Cornwall approve onshore wind schemes?

Yes — of the 35 onshore wind schemes Cornwall has decided, 74% were approved (26 granted, 9 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Cornwall?

The median time from application to decision is 7.5 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Cornwall consented?

143 MW has been consented across 26 approved schemes, with 79 MW refused. A further 14 applications awaits a decision.

Other technologies in Cornwall

Solar in CornwallBattery storage in Cornwall

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.