Solar planning in East Riding of Yorkshire
East Riding of Yorkshire has decided 57 solar farms and approved 100% of them, taking a median of 2.2 months to decide. Consented capacity: 681 MW. 8 applications still awaiting a decision.
How East Riding of Yorkshire compares
Against the 298 UK authorities with 5+ solar decisions, East Riding of Yorkshire sits in the 77th percentile for approval rate (7 points above the England average) and the 54th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (68)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Bayram Timber Limited, Gibson Lane South - Solar Panels Footprint Zero · 26/00355/PVNOT | 1.7 | Application Submitted | 2026-02-11 |
Melton Enterprise Park, Redcliff Road - Solar Panels Private Developer · 25/03552/PVNOT · 1.6 mo to decide | 0.26 | Awaiting Construction | 2026-02-06 |
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farm Enviromena Project Management UK Limited · 24/01484/STPLF · 19.1 mo to decide | 35 | Awaiting Construction | 2026-01-30 |
Sand Le Mere Holiday Village, Southfield Lane - Solar Panels Park Holidays UK Limited · 25/03410/PVNOT · 1.8 mo to decide | 0.27 | Awaiting Construction | 2026-01-27 |
Withernsea High School, Hull Road - Solar Panels Withernsea High School · 25/03123/PVNOT · 1.5 mo to decide | 0.3 | Awaiting Construction | 2025-12-15 |
Greenlands Farm, Barmby Moor - Solar Photovoltaic Arrays R S Cockerill Limited · 25/02476/PVNOT · 1.5 mo to decide | 0.29 | Awaiting Construction | 2025-10-13 |
Harbour Farm - Solar Farm Grupotec · 25/02255/STPLFE | 42 | Application Submitted | 2025-09-17 |
Kenley House Farm, Ferry Road - Solar Farm Lighthouse Development Consulting · 25/02275/STPLF | 49.9 | Application Submitted | 2025-08-21 |
Ryedale Farm, Seaton Common Lane - Solar Panels Ryedale Organics Limited · 25/01948/PVNOT · 1.2 mo to decide | 0.3 | Awaiting Construction | 2025-08-18 |
Carr Lane, Tickton - Solar Farm Albanwise Synergy Limited · 22/03648/STPLF · 31.3 mo to decide | 49.9 | Awaiting Construction | 2025-07-18 |
Neat Marsh North, Neat Marsh Road - Solar Farm Neat Marsh Solar Limited · 25/01811/STPLF | 49.9 | Application Submitted | 2025-07-18 |
Tesco Distribution Centre. Tom Pudding Way - Solar PV Array Tritax Acquisition 22 Limited · 25/01572/PVNOT · 1.5 mo to decide | 0.6 | Awaiting Construction | 2025-07-17 |
St Helens Farm, Reangamoor Lane - Solar Panels A & K Wielkopolski · 25/01410/PVNOT · 1.8 mo to decide | 0.3 | Awaiting Construction | 2025-07-11 |
Newton Farm, Tongue Lane - Solar Farm & Battery Storage Newstead Farm · 24/02946/PLF · 5.7 mo to decide | 1.5 | Awaiting Construction | 2025-06-11 |
E B Bradshaw And Sons, Bell Mills - Solar Panels Eon UK Plc · 25/00474/PLF · 3 mo to decide | 0.85 | Awaiting Construction | 2025-06-02 |
Wienerberger Limited, Tongue Lane - Solar Panels Wienerberger Limited · 25/00699/PLF | 4.7 | Application Withdrawn | 2025-05-29 |
Rawcliffe Estate, Bridge Lane - Solar Farm East Riding of Yorkshire Council (Goole Division) · 24/01628/REG3 · 4 mo to decide | 6 | Awaiting Construction | 2024-12-06 |
B W Industries Limited, Carnaby Industrial Estate - Solar Panels B W Industries Limited · 24/02817/PVNOT · 1.6 mo to decide | 0.1 | Awaiting Construction | 2024-11-15 |
Froghall Farm, Wyton Road - Solar Farm & Battery Energy Storage GAM Capital Limited · 23/00760/STPLFE · 19.5 mo to decide | 49.9 | Awaiting Construction | 2024-11-11 |
Victory Conversions, Sandholme Business Park - Solar Panels J R Rix & Sons Limited · 24/02120/PVNOT · 1.6 mo to decide | 0.41 | Awaiting Construction | 2024-09-13 |
Newland Farm, Station Road - Solar Photovoltaic Array Hardcastle & Son Limited · 24/02351/PVNOT | 0.31 | Application Submitted | 2024-08-13 |
Robinson Contract Services, Catfoss Industrial Estate - Solar Panels Robinson Builders Merchants · 24/01430/STPLF · 1.7 mo to decide | 0.97 | Awaiting Construction | 2024-07-19 |
Turf Carr Solar Farm Anesco Limited · 22/02775/STPLF · 20.5 mo to decide | 49.9 | Awaiting Construction | 2024-05-29 |
Springdale Farm, High Street - Solar Panels W D Sellers And Son · 24/00875/PVNOT · 1.6 mo to decide | 0.53 | Awaiting Construction | 2024-05-14 |
Cold Harbour Farm, Cold Harbour Road - Solar PV Array E Dunning & Son · 23/03845/PLF · 4.1 mo to decide | 0.27 | Awaiting Construction | 2024-04-16 |
Spire Hospital, Lowfield Road - Solar panels Spire Hospital · 24/00630/PVNOT · 1.2 mo to decide | 0.29 | Awaiting Construction | 2024-04-11 |
Old Chalk Pit, West Back Side - Three Oaks Renewable Park Ridge Clean Energy Limited · 22/02777/STPLF · 16.9 mo to decide | 39 | Awaiting Construction | 2024-03-21 |
Howdens Joinery, Thorpe Road - Solar Panels Howden Joinery Properties Limited · 24/00216/PVNOT · 1.3 mo to decide | 2.95 | Awaiting Construction | 2024-03-06 |
Snuff Mill Lane Gates - Solar Farm & Battery Storage UOH Energy Co Limited · 23/02046/STPLF | 9.71 | Application Withdrawn | 2024-03-05 |
Croxby Hall Farm, Inglemire Lane - Solar Farm & Battery Storage UOH Energy Co Limited · 23/02045/STPLF | 9.71 | Application Withdrawn | 2024-03-05 |
Yorkshire Grown Produce, Main Road - Solar Panels Yorkshire Grown Produce Limited · 24/00009/PVNOT · 1.7 mo to decide | 1.5 | Awaiting Construction | 2024-02-22 |
Church Hill Farm, Church Hill - Solar Array T Soanes & Son · 23/02949/PLF · 2.4 mo to decide | 0.83 | Awaiting Construction | 2024-01-11 |
Croda Europe, Tom Pudding Way - Solar Panels Croda Europe Limited · 23/01595/PLF · 4.1 mo to decide | 0.29 | Awaiting Construction | 2023-10-23 |
Cottingham Water Pumping Station, Mill House - Solar Array Yorkshire Water · 23/01363/CLP · 3.6 mo to decide | 0.37 | Awaiting Construction | 2023-09-29 |
Carr House Farm, Drove Lane - Solar Panels Private Developer · 23/01533/PLF · 1.7 mo to decide | 49.9 | Awaiting Construction | 2023-09-01 |
Country Style Foods, Carnaby Industrial Estate - Solar Panels On Site Energy Limited · 23/02214/PVNOT · 1.2 mo to decide | 0.4 | Awaiting Construction | 2023-08-31 |
Bridlington Waste Water Treatment Works - Solar Array Yorkshire Water · 23/01362/CLP · 2 mo to decide | — | Awaiting Construction | 2023-08-11 |
Modular & Portable Buildings Hire Limited, Brandesburton - Solar Panels Premier Modular Excellence Limited · 23/01527/PVNOT · 2 mo to decide | 0.38 | Awaiting Construction | 2023-08-04 |
Commons Farm, Thorne Road - Solar Panels C S Backhouse · 23/01440/PLF · 1.7 mo to decide | 0.36 | Awaiting Construction | 2023-07-27 |
Greenland Hall Farm � Ground Mounted Solar Panels CS Backhouse · 23/01427/PLF · 2.1 mo to decide | — | Awaiting Construction | 2023-07-14 |
A B Graphic International Limited , Wadsworth Road - Solar PV Panels AB Graphic International Limited · 23/01465/PVNOT · 1.7 mo to decide | 0.29 | Awaiting Construction | 2023-07-06 |
Grange Farm, Finchcroft Lane - Solar Panels J Byass and Sons · 23/01074/PLF · 1.8 mo to decide | 0.36 | Awaiting Construction | 2023-06-13 |
Thornwick Bay Holiday Village, North Marine Road - Solar Panels Bourne Leisure Limited · 23/00692/PVNOT · 2.2 mo to decide | 0.42 | Awaiting Construction | 2023-05-23 |
Sunderlandwick Solar Farm Elgin Energy EsCo Limited · 22/02460/STPLF · 7.9 mo to decide | 49.9 | Awaiting Construction | 2023-04-21 |
Far Grange Caravan Park, Hornsea Road - Solar Panels Bourne Leisure Limited · 23/00583/PVNOT · 0.8 mo to decide | 0.21 | Awaiting Construction | 2023-04-18 |
Country Style Foods, Carnaby Industrial Estate - Solar Array CSF Energy Centres · 23/00782/CLP | 0.4 | Revised | 2023-04-17 |
Luxinar Limited, Rofin House - Solar PV Panels Luxinar Limited · 23/00356/PVNOT · 1.8 mo to decide | 0.38 | Awaiting Construction | 2023-04-05 |
Ab Graphic International, Carnaby Industrial Estate - Solar Panels AB Graphic International Limited · 22/03952/PVNOT · 1.6 mo to decide | — | Awaiting Construction | 2023-01-24 |
The Oaks Golf Club - Solar Panels The Oaks Golf Club · 22/00180/PLF · 10.3 mo to decide | 0.2 | Awaiting Construction | 2022-11-30 |
Soay Solar Farm and Greener Grid Park Statkraft Uk Limited · 21/04505/STPLF · 10.1 mo to decide | 49.99 | Under Construction | 2022-11-28 |
Kenley Solar Farm Boom Power Limited · 22/01208/STPLF · 6 mo to decide | 49.9 | Awaiting Construction | 2022-11-18 |
Dalton Gates Farm, North Dalton Road - Solar Panels Warter Priory Estate · 22/03026/PVNOT · 1.8 mo to decide | 0.43 | Awaiting Construction | 2022-11-03 |
Bowmar Carr Road, Burton Pidsea - Solar Array BeBa Energy UK Limited · 22/01199/PLF · 4.7 mo to decide | 1 | Awaiting Construction | 2022-10-27 |
Field House Solar Farm Albanwise Synergy Limited · 22/00824/STPLF · 3.5 mo to decide | 40 | Awaiting Construction | 2022-07-08 |
Bessingby Road - solar photovoltaic panels York Teaching Hospital Facilities Management Llp · 22/01092/PLF | 0.24 | Application Submitted | 2022-04-26 |
Bessingby Road - solar photovoltaic panels York Teaching Hospital Facilities Management Llp · 22/01092/PLF | 0.37 | Application Submitted | 2022-04-26 |
Wingfield Way - Solar Panels WM Morrisons Supermarkets Plc · 22/00363/PVNOT · 1.8 mo to decide | 0.6 | Awaiting Construction | 2022-03-29 |
Cottingham - Solar Farm Hull & East Yorkshire Hospitals NHS Trust · 21/02126/STPLF · 9.2 mo to decide | 5 | Operational | 2022-03-14 |
Creyke Beck Substation - Solar Farm & Battery Storage Albanwise Synergy Limited · 21/02335/STPLF · 5.1 mo to decide | 49.9 | Awaiting Construction | 2022-01-06 |
South Shore Holiday Village East Riding of Yorkshire Council · 19/01883/REG3 · 17.7 mo to decide | 0.4 | Operational | 2020-12-14 |
The Gardens Warter Priory Farms · 19/04018/PLF · 11.1 mo to decide | 0.3 | Planning Permission Expired | 2020-11-06 |
Back Lane, Skerne - Solar Farm & Battery Storage BayWa r.e. UK Limited · 20/01962/STPLF · 3.4 mo to decide | 45 | Awaiting Construction | 2020-10-23 |
Scurf Dyke - Solar Farm BayWa r.e. UK Limited · 19/04321/STPLF · 2.1 mo to decide | 49.9 | Awaiting Construction | 2020-03-18 |
Hull Solar Farm Gridserve · 15/01752/STPLF · 4.3 mo to decide | 25.7 | Under Construction | 2015-10-15 |
Land at Pollington Airfield Lightsource Renewable Energy · 15/01403/STPLF · 2.3 mo to decide | 5 | Operational | 2015-07-24 |
Pollington Solar Farm Pollington Solar · 15/01315/STPLF · 2.7 mo to decide | 5 | Operational | 2015-07-17 |
Redhall Industrial Estate Dodds Limited · 12/04362/STPLF · 3 mo to decide | 5 | Operational | 2013-01-21 |
Normandy Barracks Ministry of Defence | 2.3 | Under Construction | — |
Does East Riding of Yorkshire approve solar farms?
Yes — of the 57 solar farms East Riding of Yorkshire has decided, 100% were approved (57 granted, 0 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in East Riding of Yorkshire?
The median time from application to decision is 2.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has East Riding of Yorkshire consented?
681 MW has been consented across 57 approved schemes. A further 8 applications awaits a decision.
Other technologies in East Riding of Yorkshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.