Planning and build timeline

Application submitted2018-11-16
Permission granted2020-05-28
18 months after submission
Operational2025-07-01
61 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

The Planning Inspectorate - National Infrastructure’s record on battery storage

The Planning Inspectorate - National Infrastructure has decided 19 battery storage schemes and approved 100%, taking a median of 17.4 months. See every battery storage scheme decision in The Planning Inspectorate - National Infrastructure

Other built sites within 15 km

SiteMWDistance
Cleve Hill Solar Project
Solar Photovoltaics · Operational
3730 km
Abbey Fields Farm
Solar Photovoltaics · Operational
5.32.4 km
Old Rides solar Farm
Solar Photovoltaics · Operational
86.8 km
New Rides Wind Farm
Wind Onshore · Operational
8.87.3 km
HMP Standford Hill
Wind Onshore · Operational
4.67.6 km
Tonge Corner Farm
Solar Photovoltaics · Operational
229.4 km
Plot 2B EurolinkV
Battery · Under Construction
2010.1 km
South Lees Farm
Solar Photovoltaics · Operational
1110.2 km

How big is Cleve Hill Solar Project?

Cleve Hill Solar Project has a recorded installed capacity of 150 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cleve Hill Solar Project?

REPD records the operator as Quinbrook Infrastructure Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cleve Hill Solar Project approved and built?

The application was submitted on 2018-11-16. Permission was granted on 2020-05-28, 18 months later. The site became operational on 2025-07-01, 61 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7856.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council