Renewable sitesNew Rides Wind Farm

New Rides Wind Farm

New Rides Wind Farm is operational in Swale with a recorded capacity of 8.8 MW, and has been generating since 2018-12-01.

8.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-12-01
Wind Onshore
Technology
Airvolution Energy
Swale
Authority
England

Planning and build timeline

Application submitted2014-01-27
Permission granted2017-08-09
42 months after submission
Operational2018-12-01
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Old Rides solar Farm
Solar Photovoltaics · Operational
80.6 km
HMP Standford Hill
Wind Onshore · Operational
4.60.9 km
South Lees Farm
Solar Photovoltaics · Operational
114 km
Land off Queenborough Road
Battery · Under Construction
406.8 km
Cleve Hill Solar Project
Solar Photovoltaics · Operational
3737.3 km
Cleve Hill Solar Project
Battery · Operational
1507.3 km
Tonge Corner Farm
Solar Photovoltaics · Operational
227.3 km
Ridham CHP Plant
Biomass (dedicated) · Operational
257.4 km

How big is New Rides Wind Farm?

New Rides Wind Farm has a recorded installed capacity of 8.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates New Rides Wind Farm?

REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was New Rides Wind Farm approved and built?

The application was submitted on 2014-01-27. Permission was granted on 2017-08-09, 42 months later. The site became operational on 2018-12-01, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4403.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council