Renewable sites › Tonge Corner Farm
Tonge Corner Farm
Tonge Corner Farm is operational in Swale with a recorded capacity of 22 MW, and has been generating since 2016-03-30.
Planning and build timeline
| Application submitted | 2014-03-11 |
| Permission granted | 2015-08-28 18 months after submission |
| Operational | 2016-03-30 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Swale’s record on solar
Swale has decided 26 solar farms and approved 96%, taking a median of 2.5 months. See every solar farm decision in Swale →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Plot 2B EurolinkV Battery · Under Construction | 20 | 1.3 km |
K3 CHP Facility (Kemsley EfW) EfW Incineration · Operational | 49.9 | 2 km |
Kemsley Substation Battery · Operational | 49.9 | 3 km |
Morrisons roof mounted solar Solar Photovoltaics · Operational | 2 | 3.1 km |
Ridham CHP Plant Biomass (dedicated) · Operational | 25 | 3.4 km |
South Lees Farm Solar Photovoltaics · Operational | 11 | 5.5 km |
Orchard Farm Solar Photovoltaics · Operational | 10 | 5.9 km |
Land off Queenborough Road Battery · Under Construction | 40 | 6 km |
How big is Tonge Corner Farm?
Tonge Corner Farm has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tonge Corner Farm?
REPD records the operator as Martifer Solar (Voltalia). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tonge Corner Farm approved and built?
The application was submitted on 2014-03-11. Permission was granted on 2015-08-28, 18 months later. The site became operational on 2016-03-30, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1924.