Renewable sites › South Lees Farm
South Lees Farm
South Lees Farm is operational in Swale with a recorded capacity of 11 MW, and has been generating since 2014-06-22.
Planning and build timeline
| Application submitted | 2013-10-04 |
| Permission granted | 2014-01-22 4 months after submission |
| Operational | 2014-06-22 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Swale’s record on solar
Swale has decided 26 solar farms and approved 96%, taking a median of 2.5 months. See every solar farm decision in Swale →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land off Queenborough Road Battery · Under Construction | 40 | 2.8 km |
HMP Standford Hill Wind Onshore · Operational | 4.6 | 3.2 km |
Ridham CHP Plant Biomass (dedicated) · Operational | 25 | 3.9 km |
New Rides Wind Farm Wind Onshore · Operational | 8.8 | 4 km |
Old Rides solar Farm Solar Photovoltaics · Operational | 8 | 4.5 km |
K3 CHP Facility (Kemsley EfW) EfW Incineration · Operational | 49.9 | 5.1 km |
Morrisons roof mounted solar Solar Photovoltaics · Operational | 2 | 5.4 km |
Tonge Corner Farm Solar Photovoltaics · Operational | 22 | 5.5 km |
How big is South Lees Farm?
South Lees Farm has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates South Lees Farm?
REPD records the operator as Solar Century. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was South Lees Farm approved and built?
The application was submitted on 2013-10-04. Permission was granted on 2014-01-22, 4 months later. The site became operational on 2014-06-22, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1767.
Novarly Parcel · official public data, read properly · parcel.novarly.com