Cleve Hill Solar Project

Cleve Hill Solar Project is an operational 373 MW solar farm in England, generating since 1 July 2025. Planning permission was granted on 29 January 2021, 26 months after submission. Operator of record: Quinbrook Infrastructure Partners.

373 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2025
Solar Photovoltaics
Technology
Quinbrook Infrastructure Partners
National
Authority
England

Planning and build timeline

Application submitted16 November 2018
Permission granted29 January 2021
26 months after submission
Operational1 July 2025
53 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cleve Hill Solar Project’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

The Planning Inspectorate - National Infrastructure’s record on solar

The Planning Inspectorate - National Infrastructure has decided 18 solar farms and approved 100%, taking a median of 17.4 months. See every solar farm decision in The Planning Inspectorate - National Infrastructure

Other built sites within 15 km

SiteMWDistance
Battery · Operational
1500 km
Solar Photovoltaics · Operational
5.32.4 km
Solar Photovoltaics · Operational
86.8 km
Wind Onshore · Operational
8.87.3 km
Wind Onshore · Operational
4.67.6 km
Solar Photovoltaics · Operational
229.4 km
Battery · Under Construction
2010.1 km
Solar Photovoltaics · Operational
1110.2 km

How big is Cleve Hill Solar Project?

Cleve Hill Solar Project has a recorded installed capacity of 373 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cleve Hill Solar Project?

REPD records the operator as Quinbrook Infrastructure Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cleve Hill Solar Project approved and built?

The application was submitted on 16 November 2018. Permission was granted on 29 January 2021, 26 months later. The site became operational on 1 July 2025, 53 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6502.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode