Eco Composting

Eco Composting is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 3.2 MW, and has been generating since 2017-03-22.

3.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-22
Biomass (dedicated)
Technology
Eco Sustainable Solutions
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted2011-05-26
Permission granted2011-07-26
2 months after submission
Operational2017-03-22
68 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Chapel Lane ERF
EfW Incineration · Under Construction
3.40.5 km
Chapel Lane Parley Solar Farm Phase 1
Solar Photovoltaics · Operational
200.7 km
Hale Farm
Solar Photovoltaics · Operational
81 km
Chapel Lane Parley Solar Farm Phase 2
Solar Photovoltaics · Operational
361.1 km
Woodtown Farm
Solar Photovoltaics · Operational
3.81.5 km
Chapel Lane Parley Solar Farm Phase 3
Solar Photovoltaics · Operational
42 km
Bedborough Farm
Solar Photovoltaics · Operational
75.9 km
Homeland Solar Farm
Solar Photovoltaics · Operational
13.26.8 km

How big is Eco Composting?

Eco Composting has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Eco Composting?

REPD records the operator as Eco Sustainable Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Eco Composting approved and built?

The application was submitted on 2011-05-26. Permission was granted on 2011-07-26, 2 months later. The site became operational on 2017-03-22, 68 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 139.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council