Hale Farm is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 8 MW, and has been generating since 2016-02-26.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-26
Solar Photovoltaics
Technology
Hale Solar Limited
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted2014-10-28
Permission granted2015-09-23
11 months after submission
Operational2016-02-26
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bournemouth, Christchurch and Poole’s record on solar

Bournemouth, Christchurch and Poole has decided 25 solar farms and approved 88%, taking a median of 2.3 months. See every solar farm decision in Bournemouth, Christchurch and Poole

Other built sites within 15 km

SiteMWDistance
Woodtown Farm
Solar Photovoltaics · Operational
3.80.6 km
Eco Composting
Biomass (dedicated) · Operational
3.21 km
Chapel Lane ERF
EfW Incineration · Under Construction
3.41.5 km
Chapel Lane Parley Solar Farm Phase 1
Solar Photovoltaics · Operational
201.5 km
Chapel Lane Parley Solar Farm Phase 2
Solar Photovoltaics · Operational
362 km
Chapel Lane Parley Solar Farm Phase 3
Solar Photovoltaics · Operational
42.8 km
Bedborough Farm
Solar Photovoltaics · Operational
76.1 km
Dorset Green Solar Farm
Solar Photovoltaics · Operational
56.2 km

How big is Hale Farm?

Hale Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hale Farm?

REPD records the operator as Hale Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hale Farm approved and built?

The application was submitted on 2014-10-28. Permission was granted on 2015-09-23, 11 months later. The site became operational on 2016-02-26, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4727.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council