Renewable sites › Bumpers Farm Phase 1
Bumpers Farm Phase 1
Bumpers Farm Phase 1 is operational in Buckinghamshire with a recorded capacity of 5 MW, and has been generating since 2017-03-25.
Planning and build timeline
| Application submitted | 2014-07-11 |
| Permission granted | 2015-10-26 16 months after submission |
| Operational | 2017-03-25 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Buckinghamshire’s record on solar
Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bumpers Lane Solar Farm Battery · Operational | 13.3 | 0.6 km |
Thame solar farm Solar Photovoltaics · Operational | 4.3 | 2.7 km |
The Oxfordshire Golf Club Solar Photovoltaics · Operational | 0.3 | 8.5 km |
Quarrendon Fields Wind Onshore · Operational | 1.5 | 11.3 km |
Westcott Venture Park Phase 2 & 3 Solar Photovoltaics · Operational | 1.3 | 11.6 km |
Westcott Venture Park Anaerobic Digestion · Operational | 2 | 12.6 km |
Gib Lane (Aston Clinton solar park) Solar Photovoltaics · Operational | 24.2 | 13.2 km |
Arla Dairy Site Anaerobic Digestion · Operational | 5 | 13.6 km |
How big is Bumpers Farm Phase 1?
Bumpers Farm Phase 1 has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bumpers Farm Phase 1?
REPD records the operator as Solar Planning. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bumpers Farm Phase 1 approved and built?
The application was submitted on 2014-07-11. Permission was granted on 2015-10-26, 16 months later. The site became operational on 2017-03-25, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2186.