Novarly ParcelRenewable sites

Renewable sitesThame solar farm

Thame solar farm

Thame solar farm is operational in South Oxfordshire with a recorded capacity of 4.3 MW, and has been generating since 2016-12-16.

4.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-16
Solar Photovoltaics
Technology
Big 60 Million
South Oxfordshire
Authority
England

Planning and build timeline

Application submitted2014-07-17
Permission granted2015-10-29
15 months after submission
Operational2016-12-16
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Oxfordshire’s record on solar

South Oxfordshire has decided 22 solar farms and approved 95%, taking a median of 4.2 months. See every solar farm decision in South Oxfordshire

Other built sites within 15 km

SiteMWDistance
Bumpers Farm Phase 1
Solar Photovoltaics · Operational
52.7 km
Bumpers Lane Solar Farm
Battery · Operational
13.33 km
The Oxfordshire Golf Club
Solar Photovoltaics · Operational
0.36 km
Westcott Venture Park Phase 2 & 3
Solar Photovoltaics · Operational
1.311 km
Westcott Venture Park
Anaerobic Digestion · Operational
211.8 km
Easington Farm (Chalgrove)
Solar Photovoltaics · Operational
21.312.2 km
Quarrendon Fields
Wind Onshore · Operational
1.512.5 km
Langley Hall Farm
Solar Photovoltaics · Operational
2.414.7 km

How big is Thame solar farm?

Thame solar farm has a recorded installed capacity of 4.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thame solar farm?

REPD records the operator as Big 60 Million. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thame solar farm approved and built?

The application was submitted on 2014-07-17. Permission was granted on 2015-10-29, 15 months later. The site became operational on 2016-12-16, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2068.