Renewable sitesArla Dairy Site

Arla Dairy Site

Arla Dairy Site is an operational 5 MW anaerobic digestion plant in Buckinghamshire, generating since 1 August 2017. Planning permission was granted on 15 July 2015, 7 months after submission. Operator of record: Olleco and Arla Foods.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2017
Anaerobic Digestion
Technology
Olleco and Arla Foods
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted11 December 2014
Permission granted15 July 2015
7 months after submission
Operational1 August 2017
25 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Buckinghamshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Arla Dairy Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.8 km
Solar Photovoltaics · Operational
24.21.2 km
Solar Photovoltaics · Operational
13.12.1 km
Solar Photovoltaics · Operational
4.16.8 km
Solar Photovoltaics · Operational
57 km
Wind Onshore · Operational
1.57.2 km
Solar Photovoltaics · Operational
6.29.2 km
Battery · Operational
13.313 km

How big is Arla Dairy Site?

Arla Dairy Site has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arla Dairy Site?

REPD records the operator as Olleco and Arla Foods. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arla Dairy Site approved and built?

The application was submitted on 11 December 2014. Permission was granted on 15 July 2015, 7 months later. The site became operational on 1 August 2017, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4906.