Arla Dairy Site

Arla Dairy Site is operational in Buckinghamshire with a recorded capacity of 5 MW, and has been generating since 2017-08-01.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-08-01
Anaerobic Digestion
Technology
Olleco and Arla Foods
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted2014-12-11
Permission granted2015-07-15
7 months after submission
Operational2017-08-01
25 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Gib Lane Solar farm (Extension)
Solar Photovoltaics · Operational
50.8 km
Gib Lane (Aston Clinton solar park)
Solar Photovoltaics · Operational
24.21.2 km
Folly Farm
Solar Photovoltaics · Operational
13.12.1 km
Long Meadow Farm
Solar Photovoltaics · Operational
4.16.8 km
Great Seabrook Farm
Solar Photovoltaics · Operational
57 km
Quarrendon Fields
Wind Onshore · Operational
1.57.2 km
Church Farm
Solar Photovoltaics · Operational
6.29.2 km
Bumpers Lane Solar Farm
Battery · Operational
13.313 km

How big is Arla Dairy Site?

Arla Dairy Site has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arla Dairy Site?

REPD records the operator as Olleco and Arla Foods. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arla Dairy Site approved and built?

The application was submitted on 2014-12-11. Permission was granted on 2015-07-15, 7 months later. The site became operational on 2017-08-01, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4906.

Novarly Parcel · official public data, read properly · parcel.novarly.com