Renewable sitesGib Lane (Aston Clinton solar park)

Gib Lane (Aston Clinton solar park)

Gib Lane (Aston Clinton solar park) is operational in Buckinghamshire with a recorded capacity of 24.2 MW, and has been generating since 2015-03-30.

24.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-30
Solar Photovoltaics
Technology
CEE
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted2014-08-11
Permission granted2014-11-12
3 months after submission
Operational2015-03-30
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Buckinghamshire’s record on solar

Buckinghamshire has decided 59 solar farms and approved 90%, taking a median of 3 months. See every solar farm decision in Buckinghamshire

Other built sites within 15 km

SiteMWDistance
Arla Dairy Site
Anaerobic Digestion · Operational
51.2 km
Gib Lane Solar farm (Extension)
Solar Photovoltaics · Operational
51.9 km
Folly Farm
Solar Photovoltaics · Operational
13.13.2 km
Long Meadow Farm
Solar Photovoltaics · Operational
4.17.1 km
Great Seabrook Farm
Solar Photovoltaics · Operational
57.4 km
Quarrendon Fields
Wind Onshore · Operational
1.57.9 km
Church Farm
Solar Photovoltaics · Operational
6.29.8 km
Bumpers Lane Solar Farm
Battery · Operational
13.312.7 km

How big is Gib Lane (Aston Clinton solar park)?

Gib Lane (Aston Clinton solar park) has a recorded installed capacity of 24.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Gib Lane (Aston Clinton solar park)?

REPD records the operator as CEE. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Gib Lane (Aston Clinton solar park) approved and built?

The application was submitted on 2014-08-11. Permission was granted on 2014-11-12, 3 months later. The site became operational on 2015-03-30, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2239.