Renewable sites › Westcott Venture Park
Westcott Venture Park
Westcott Venture Park is operational in Buckinghamshire with a recorded capacity of 2 MW, and has been generating since 2013-11-07.
Planning and build timeline
| Application submitted | 2010-05-24 |
| Permission granted | 2010-07-09 2 months after submission |
| Operational | 2013-11-07 40 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Westcott Venture Park Phase 2 & 3 Solar Photovoltaics · Operational | 1.3 | 1.6 km |
Calvert Phase II Landfill Gas · Operational | 11.2 | 5.7 km |
Greatmoor EfW EfW Incineration · Operational | 22 | 7.3 km |
Quarrendon Fields Wind Onshore · Operational | 1.5 | 9.9 km |
Ray Valley Solar Farm Solar Photovoltaics · Under Construction | 19 | 10.2 km |
Ray Valley Solar Farm Battery · Under Construction | — | 10.2 km |
Brooks Farm Solar Park Solar Photovoltaics · Operational | 8 | 10.6 km |
Home Farm (Merton - solar) Solar Photovoltaics · Operational | 18.3 | 11.5 km |
How big is Westcott Venture Park?
Westcott Venture Park has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Westcott Venture Park?
REPD records the operator as Olleco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Westcott Venture Park approved and built?
The application was submitted on 2010-05-24. Permission was granted on 2010-07-09, 2 months later. The site became operational on 2013-11-07, 40 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 283.
Novarly Parcel · official public data, read properly · parcel.novarly.com