Renewable sites › Branston Solar Park (extension)
Branston Solar Park (extension)
Branston Solar Park (extension) is under construction in North Kesteven with a recorded capacity of 40 MW.
Planning and build timeline
| Application submitted | 2017-10-23 |
| Permission granted | 2017-12-19 2 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Kesteven’s record on solar
North Kesteven has decided 26 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in North Kesteven →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Branston solar park Solar Photovoltaics · Operational | 18.9 | 0.6 km |
Metheringham Heath (Farm AD) Anaerobic Digestion · Operational | 6.5 | 5.6 km |
Fiskerton Airfield (Phase 2) Solar Photovoltaics · Operational | 22 | 7.1 km |
Fiskerton Airfield (Phase 1) Solar Photovoltaics · Operational | 12 | 7.1 km |
Top Farm, Short Ferry Road - Solar PV Arrays Solar Photovoltaics · Under Construction | 0.86 | 9.4 km |
Lincoln EFW EfW Incineration · Operational | 16.4 | 9.6 km |
Lincoln Landfill Scheme Landfill Gas · Operational | 2 | 9.7 km |
Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building Biomass (dedicated) · Under Construction | 1.6 | 10.3 km |
How big is Branston Solar Park (extension)?
Branston Solar Park (extension) has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Branston Solar Park (extension)?
REPD records the operator as Ethical Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Branston Solar Park (extension) approved and built?
The application was submitted on 2017-10-23. Permission was granted on 2017-12-19, 2 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6456.
Novarly Parcel · official public data, read properly · parcel.novarly.com