Novarly ParcelRenewable sites

Renewable sitesBranston solar park

Branston solar park

Branston solar park is operational in North Kesteven with a recorded capacity of 18.9 MW, and has been generating since 2015-03-31.

18.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-31
Solar Photovoltaics
Technology
Inazin Energy Limited/Low Carbon
North Kesteven
Authority
England

Planning and build timeline

Application submitted2014-06-02
Permission granted2014-10-15
4 months after submission
Operational2015-03-31
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Kesteven’s record on solar

North Kesteven has decided 26 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in North Kesteven

Other built sites within 15 km

SiteMWDistance
Branston Solar Park (extension)
Solar Photovoltaics · Under Construction
400.6 km
Metheringham Heath (Farm AD)
Anaerobic Digestion · Operational
6.55.3 km
Fiskerton Airfield (Phase 1)
Solar Photovoltaics · Operational
127.6 km
Fiskerton Airfield (Phase 2)
Solar Photovoltaics · Operational
227.6 km
Lincoln EFW
EfW Incineration · Operational
16.49.1 km
Lincoln Landfill Scheme
Landfill Gas · Operational
29.2 km
Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building
Biomass (dedicated) · Under Construction
1.69.7 km
Top Farm, Short Ferry Road - Solar PV Arrays
Solar Photovoltaics · Under Construction
0.8610 km

How big is Branston solar park?

Branston solar park has a recorded installed capacity of 18.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Branston solar park?

REPD records the operator as Inazin Energy Limited/Low Carbon. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Branston solar park approved and built?

The application was submitted on 2014-06-02. Permission was granted on 2014-10-15, 4 months later. The site became operational on 2015-03-31, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2323.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council