Novarly ParcelRenewable sites

Renewable sitesCastle Farm, Castle Lane - Biomass Boiler & Agricultural Building

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building is under construction in North Kesteven with a recorded capacity of 1.6 MW.

1.6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Biomass (dedicated)
Technology
G.E. Porter & Sons Limited
North Kesteven
Authority
England

Planning and build timeline

Application submitted2022-08-19
Permission granted2023-06-06
10 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Skinnand Manor Farm, Parsons Lane - Biomass Boiler
Biomass (dedicated) · Under Construction
1.61.7 km
Metheringham Heath (Farm AD)
Anaerobic Digestion · Operational
6.56.9 km
Lincoln Landfill Scheme
Landfill Gas · Operational
29.3 km
Lincoln EFW
EfW Incineration · Operational
16.49.4 km
Branston solar park
Solar Photovoltaics · Operational
18.99.7 km
Branston Solar Park (extension)
Solar Photovoltaics · Under Construction
4010.3 km
Ermine Street Farm solar park
Solar Photovoltaics · Operational
32.511.8 km

How big is Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building?

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building?

REPD records the operator as G.E. Porter & Sons Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building approved and built?

The application was submitted on 2022-08-19. Permission was granted on 2023-06-06, 10 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12052.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council