Novarly ParcelRenewable sites

Renewable sitesCastle Farm, Castle Lane - Biomass Boiler & Agricultural Building

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building is a 1.6 MW biomass plant under construction in North Kesteven. Planning permission was granted on 6 June 2023, 10 months after submission. Operator of record: G.E. Porter & Sons Limited.

1.6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Biomass (dedicated)
Technology
G.E. Porter & Sons Limited
North Kesteven
Authority
England

Planning and build timeline

Application submitted19 August 2022
Permission granted6 June 2023
10 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in North Kesteven: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Under Construction
1.61.7 km
Anaerobic Digestion · Operational
6.56.9 km
Landfill Gas · Operational
29.3 km
EfW Incineration · Operational
16.49.4 km
Solar Photovoltaics · Operational
18.99.7 km
Solar Photovoltaics · Under Construction
4010.3 km
Solar Photovoltaics · Operational
32.511.8 km

How big is Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building?

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building?

REPD records the operator as G.E. Porter & Sons Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building approved and built?

The application was submitted on 19 August 2022. Permission was granted on 6 June 2023, 10 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12052.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode