Novarly ParcelRenewable sites

Renewable sitesLincoln EFW

Lincoln EFW

Lincoln EFW is operational in North Kesteven with a recorded capacity of 16.4 MW, and has been generating since 2014-03-14.

16.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-14
EfW Incineration
Technology
Lincolnshire County Council
North Kesteven
Authority
England

Planning and build timeline

Application submitted2008-11-28
Permission granted2009-03-16
4 months after submission
Operational2014-03-14
60 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Lincoln Landfill Scheme
Landfill Gas · Operational
20.3 km
Leverton Farm - Energy Barn
Battery · Operational
107.3 km
Branston solar park
Solar Photovoltaics · Operational
18.99.1 km
Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building
Biomass (dedicated) · Under Construction
1.69.4 km
Branston Solar Park (extension)
Solar Photovoltaics · Under Construction
409.6 km
Skinnand Manor Farm, Parsons Lane - Biomass Boiler
Biomass (dedicated) · Under Construction
1.610.6 km
Metheringham Heath (Farm AD)
Anaerobic Digestion · Operational
6.511.6 km
JG Pears' animal rendering facility
Biomass (dedicated) · Operational
1212.9 km

How big is Lincoln EFW?

Lincoln EFW has a recorded installed capacity of 16.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lincoln EFW?

REPD records the operator as Lincolnshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lincoln EFW approved and built?

The application was submitted on 2008-11-28. Permission was granted on 2009-03-16, 4 months later. The site became operational on 2014-03-14, 60 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 924.