Renewable sitesLincoln EFW

Lincoln EFW

Lincoln EFW is an operational 16.4 MW energy-from-waste plant in North Kesteven, generating since 14 March 2014. Planning permission was granted on 16 March 2009, 4 months after submission. Operator of record: Lincolnshire County Council.

16.4 MW
Capacity
as recorded in REPD
Operational
Status
since 14 March 2014
EfW Incineration
Technology
Lincolnshire County Council
North Kesteven
Authority
England

Planning and build timeline

Application submitted28 November 2008
Permission granted16 March 2009
4 months after submission
Operational14 March 2014
60 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in North Kesteven: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lincoln EFW’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
20.3 km
Battery · Operational
107.3 km
Solar Photovoltaics · Operational
18.99.1 km
Biomass (dedicated) · Under Construction
1.69.4 km
Solar Photovoltaics · Under Construction
409.6 km
Biomass (dedicated) · Under Construction
1.610.6 km
Anaerobic Digestion · Operational
6.511.6 km
Biomass (dedicated) · Operational
1212.9 km

How big is Lincoln EFW?

Lincoln EFW has a recorded installed capacity of 16.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lincoln EFW?

REPD records the operator as Lincolnshire County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lincoln EFW approved and built?

The application was submitted on 28 November 2008. Permission was granted on 16 March 2009, 4 months later. The site became operational on 14 March 2014, 60 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 924.