Renewable planning › Solar › North Kesteven
Solar planning in North Kesteven
North Kesteven has decided 26 solar farms and approved 100% of them, taking a median of 2.1 months to decide. Consented capacity: 347 MW. 4 applications still awaiting a decision.
How North Kesteven compares
Against the 298 UK authorities with 5+ solar decisions, North Kesteven sits in the 77th percentile for approval rate (7 points above the England average) and the 56th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (32)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Mareham Lane, Solar PV Panels Lighthouse Development Consulting · 23/1419/FUL · 26.3 mo to decide | 49.99 | Awaiting Construction | 2026-02-16 |
Whisby Quarry, Eagle Road - Solar Array Conrad Energy · PL/0130/24 · 7.9 mo to decide | 18 | Awaiting Construction | 2025-09-17 |
Little Hale Fen - Solar Farm AGR Solar 2 Limited · 23/1021/FUL · 22.9 mo to decide | 49.99 | Awaiting Construction | 2025-08-13 |
Newton Grange Farm, Newton - 6 Poultry Houses Hinch Enterprises · 25/0745/FUL | 0.6 | Application Submitted | 2025-07-02 |
Ferry Lane, Skellingthorpe - Solar Panels PS Renewables Limited · 25/0521/FUL | 20.2 | Application Submitted | 2025-05-08 |
MV Fruehauf Limited, Houghton Road - Solar Panels MV Fruehauf Limited · S25/0399 · 1.8 mo to decide | 0.48 | Application Submitted | 2025-05-02 |
Burton Gorse Plantation, Whitecross Lane - Solar Panels Starlight Energy · 24/1470/FUL | 42 | Application Submitted | 2025-03-26 |
Crofton Drive - Solar Photovoltaic Panels Rilmac Group Limited · 2025/0074/PA · 1 mo to decide | 0.43 | Awaiting Construction | 2025-03-13 |
Lincoln Bowl, Washingborough Road - Solar Panels Private Developer · 2024/0512/PA · 1.1 mo to decide | 0.21 | Awaiting Construction | 2024-09-16 |
Pilgrims UK, Sleaford Road - Solar Canopy EDF Energy Renewables · 24/0767/PNREN · 1.9 mo to decide | 0.49 | Awaiting Construction | 2024-08-29 |
Pilgrims Pride, Sleaford Road - Solar Panels EDF Energy Renewables · 24/0748/PNREN · 1.8 mo to decide | 0.73 | Awaiting Construction | 2024-08-21 |
North Kesteven Sports Centre, Moor Lane - Solar PV Panels North Kesteven District Council · 24/0580/PNREN · 1.8 mo to decide | 0.17 | Awaiting Construction | 2024-07-10 |
Beeswax Dyson Farming, Cyclone Way - Solar Arrays Dyson Farming Limited · 24/0608/PNREN · 1.8 mo to decide | 0.5 | Awaiting Construction | 2024-07-09 |
Leadenham Poultry Unit, Sleaford Road - Solar Panels Sutherland Farms Limited · 24/0306/PNREN | 0.3 | Application Withdrawn | 2024-04-23 |
The Feed Mill, Lowfields - Solar Panels J Porter & Son · 24/0235/PNREN · 1.2 mo to decide | — | Awaiting Construction | 2024-03-28 |
Swinderby Quarry - Solar PV Array CEMEX UK Properties · PL/0055/23 · 3.2 mo to decide | 1.2 | Awaiting Construction | 2023-11-13 |
Noble Foods, Hives Lane - Solar Panels Noble Foods Limited · 22/1569/FUL · 8.3 mo to decide | 0.37 | Awaiting Construction | 2023-07-14 |
Cargill & Frontier Agriculture, Camp Road - Solar Panels BeBa Energy UK Limited · 23/0110/PNREN · 1.9 mo to decide | 0.36 | Awaiting Construction | 2023-03-29 |
New Earth Solutions West, High Dike - Solar Panels & Battery Srorage New Earth Solutions (West) Limited · PL/0123/22 · 2.7 mo to decide | 4.8 | Awaiting Construction | 2023-01-31 |
Boothby Graffoe - Solar photovoltaics panels JE Porter Limited · 22/0475/PNREN · 1.8 mo to decide | 0.22 | Awaiting Construction | 2022-05-24 |
Barn Farm, Navenby - Solar Panels JE Porter Limited · 22/0447/PNREN · 1.8 mo to decide | 0.22 | Awaiting Construction | 2022-05-24 |
Skinnand Manor Farm, Navenby - Solar panels Private Developer · 22/0476/PNREN · 1.8 mo to decide | — | Awaiting Construction | 2022-05-23 |
White Cross Lane Nextpower SPV 5 Limited · 19/0863/FUL · 6.4 mo to decide | 25 | Under Construction | 2019-12-31 |
Gorse Lane Elgin Energy Esco · 19/0060/FUL · 2.4 mo to decide | 20 | Under Construction | 2019-03-29 |
Branston Solar Park (extension) Ethical Power · 17/1546/FUL · 1.9 mo to decide | 40 | Under Construction | 2017-12-19 |
White Gorse Farm Green Switch Solutions - Liquidated · 14/0954/FUL · 3.8 mo to decide | 11.6 | Planning Permission Expired | 2014-11-25 |
Deepdale Farm Deepdale Farm Solar Ltd · 14/0952/FUL · 3.8 mo to decide | 8 | Operational | 2014-11-10 |
Branston solar park Inazin Energy Limited/Low Carbon · 14/0672/FUL · 4.4 mo to decide | 18.9 | Operational | 2014-10-15 |
Ewerby Thorpe Farm Estover Energy · 14/1003/FUL · 1.9 mo to decide | 25 | Abandoned | 2014-10-03 |
Scopwick (Blankney Farm) Hazel Capital LLP · 14/0937/FUL · 2.5 mo to decide | 48 | Planning Permission Expired | 2014-09-25 |
Ermine Street Farm solar park Octopus Investments · 13/0929/FUL · 3.5 mo to decide | 32.5 | Operational | 2013-12-06 |
Grange Farm (Burton Pedwardine) Lark Energy · 12/1242/FUL · 2.3 mo to decide | 15 | Operational | 2013-02-04 |
Does North Kesteven approve solar farms?
Yes — of the 26 solar farms North Kesteven has decided, 100% were approved (26 granted, 0 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in North Kesteven?
The median time from application to decision is 2.1 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has North Kesteven consented?
347 MW has been consented across 26 approved schemes. A further 4 applications awaits a decision.
Other technologies in North Kesteven
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.