Novarly ParcelRenewable sites

Renewable sitesCramlington CHP

Cramlington CHP

Cramlington CHP is operational in Northumberland with a recorded capacity of 27.7 MW, and has been generating since 2018-03-15.

27.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-03-15
Biomass (dedicated)
Technology
Estover Energy
Northumberland
Authority
England

Planning and build timeline

Application submitted2012-08-31
Permission granted2013-01-21
5 months after submission
Operational2018-03-15
62 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
MSD Cramlington
Wind Onshore · Operational
40.7 km
Brenkley Landfill
Landfill Gas · Operational
1.94.6 km
Blyth Sewage Treatment Works
Solar Photovoltaics · Operational
2.36.6 km
Seghill Village Waste Disposal Site phase 1 and 2
Landfill Gas · Operational
4.16.7 km
County Hall, Loansdean - Solar Array
Solar Photovoltaics · Operational
0.87.4 km
County Hall, Loansdean - Battery Storage
Battery · Operational
0.47.4 km
Newcastle International Airport Phase 1 -Solar Farm
Solar Photovoltaics · Under Construction
38.3 km
Blyth Harbour Wind Farm (re-power)
Wind Onshore · Operational
3.48.5 km

How big is Cramlington CHP?

Cramlington CHP has a recorded installed capacity of 27.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cramlington CHP?

REPD records the operator as Estover Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cramlington CHP approved and built?

The application was submitted on 2012-08-31. Permission was granted on 2013-01-21, 5 months later. The site became operational on 2018-03-15, 62 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 121.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council