Novarly ParcelRenewable sites

Renewable sitesBlanche Lane, South Mimms - Solar Panels

Blanche Lane, South Mimms - Solar Panels

Blanche Lane, South Mimms - Solar Panels is under construction in Hertsmere with a recorded capacity of 0.61 MW.

0.61 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Private Developer
Hertsmere
Authority
England

Planning and build timeline

Application submitted2022-06-10
Permission granted2023-08-23
14 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Hertsmere’s record on solar

Hertsmere has decided 13 solar farms and approved 92%, taking a median of 1.8 months. See every solar farm decision in Hertsmere

Other built sites within 15 km

SiteMWDistance
Land At Swanland Road
Solar Photovoltaics · Operational
51.6 km
Potters Bar Solar Farm
Solar Photovoltaics · Operational
53.4 km
Elstree Film And TV Studios, Shenley Road - Solar Panels
Solar Photovoltaics · Operational
34 km
Coursers Farm AD Plant (Waste AD)
Anaerobic Digestion · Operational
34.4 km
Tollgate Farm Battery Storage
Battery · Under Construction
49.55.2 km
Aylett Nurseries - Solar Panels
Solar Photovoltaics · Operational
6.7 km
Cattlegate Farm Biogas (Farm AD)
Anaerobic Digestion · Operational
1.59 km
Computacenter Warehouse
Solar Photovoltaics · Under Construction
29.5 km

How big is Blanche Lane, South Mimms - Solar Panels?

Blanche Lane, South Mimms - Solar Panels has a recorded installed capacity of 0.61 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blanche Lane, South Mimms - Solar Panels?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blanche Lane, South Mimms - Solar Panels approved and built?

The application was submitted on 2022-06-10. Permission was granted on 2023-08-23, 14 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11499.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council