Novarly ParcelRenewable sites

Renewable sitesTollgate Farm Battery Storage

Tollgate Farm Battery Storage

Tollgate Farm Battery Storage is a 49.5 MW battery storage site under construction in Welwyn Hatfield. Planning permission was granted on 22 January 2019, 15 months after submission. Operator of record: RNA Energy / Harmony Energy Storage/ Tag Energy UK.

49.5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
RNA Energy / Harmony Energy Storage/ Tag Energy UK
Welwyn Hatfield
Authority
England

Planning and build timeline

Application submitted12 October 2017
Permission granted22 January 2019
15 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Welwyn Hatfield approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tollgate Farm Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Welwyn Hatfield’s record on battery storage

Welwyn Hatfield has decided 6 battery storage schemes and approved 100%, taking a median of 2.8 months. See every battery storage scheme decision in Welwyn Hatfield

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
31.7 km
Solar Photovoltaics · Operational
53.7 km
Solar Photovoltaics · Under Construction
24.4 km
Solar Photovoltaics · Operational
54.4 km
Solar Photovoltaics · Operational
5 km
Solar Photovoltaics · Under Construction
0.615.2 km
Solar Photovoltaics · Operational
38.9 km
Anaerobic Digestion · Operational
1.59.7 km

How big is Tollgate Farm Battery Storage?

Tollgate Farm Battery Storage has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tollgate Farm Battery Storage?

REPD records the operator as RNA Energy / Harmony Energy Storage/ Tag Energy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tollgate Farm Battery Storage approved and built?

The application was submitted on 12 October 2017. Permission was granted on 22 January 2019, 15 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7335.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode