Novarly ParcelRenewable sites

Renewable sitesTollgate Farm Battery Storage

Tollgate Farm Battery Storage

Tollgate Farm Battery Storage is under construction in Welwyn Hatfield with a recorded capacity of 49.5 MW.

49.5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
RNA Energy / Harmony Energy Storage/ Tag Energy UK
Welwyn Hatfield
Authority
England

Planning and build timeline

Application submitted2017-10-12
Permission granted2019-01-22
15 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Welwyn Hatfield’s record on battery storage

Welwyn Hatfield has decided 6 battery storage schemes and approved 100%, taking a median of 2.8 months. See every battery storage scheme decision in Welwyn Hatfield

Other built sites within 15 km

SiteMWDistance
Coursers Farm AD Plant (Waste AD)
Anaerobic Digestion · Operational
31.7 km
Potters Bar Solar Farm
Solar Photovoltaics · Operational
53.7 km
Computacenter Warehouse
Solar Photovoltaics · Under Construction
24.4 km
Land At Swanland Road
Solar Photovoltaics · Operational
54.4 km
Aylett Nurseries - Solar Panels
Solar Photovoltaics · Operational
5 km
Blanche Lane, South Mimms - Solar Panels
Solar Photovoltaics · Under Construction
0.615.2 km
Elstree Film And TV Studios, Shenley Road - Solar Panels
Solar Photovoltaics · Operational
38.9 km
Cattlegate Farm Biogas (Farm AD)
Anaerobic Digestion · Operational
1.59.7 km

How big is Tollgate Farm Battery Storage?

Tollgate Farm Battery Storage has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tollgate Farm Battery Storage?

REPD records the operator as RNA Energy / Harmony Energy Storage/ Tag Energy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tollgate Farm Battery Storage approved and built?

The application was submitted on 2017-10-12. Permission was granted on 2019-01-22, 15 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7335.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council