Tollgate Farm Battery Storage
Tollgate Farm Battery Storage is under construction in Welwyn Hatfield with a recorded capacity of 49.5 MW.
Planning and build timeline
| Application submitted | 2017-10-12 |
| Permission granted | 2019-01-22 15 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — Welwyn Hatfield
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Welwyn Hatfield’s record on battery storage
Welwyn Hatfield has decided 6 battery storage schemes and approved 100%, taking a median of 2.8 months. See every battery storage scheme decision in Welwyn Hatfield →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Coursers Farm AD Plant (Waste AD) Anaerobic Digestion · Operational | 3 | 1.7 km |
Potters Bar Solar Farm Solar Photovoltaics · Operational | 5 | 3.7 km |
Computacenter Warehouse Solar Photovoltaics · Under Construction | 2 | 4.4 km |
Land At Swanland Road Solar Photovoltaics · Operational | 5 | 4.4 km |
Aylett Nurseries - Solar Panels Solar Photovoltaics · Operational | — | 5 km |
Blanche Lane, South Mimms - Solar Panels Solar Photovoltaics · Under Construction | 0.61 | 5.2 km |
Elstree Film And TV Studios, Shenley Road - Solar Panels Solar Photovoltaics · Operational | 3 | 8.9 km |
Cattlegate Farm Biogas (Farm AD) Anaerobic Digestion · Operational | 1.5 | 9.7 km |
How big is Tollgate Farm Battery Storage?
Tollgate Farm Battery Storage has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tollgate Farm Battery Storage?
REPD records the operator as RNA Energy / Harmony Energy Storage/ Tag Energy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tollgate Farm Battery Storage approved and built?
The application was submitted on 2017-10-12. Permission was granted on 2019-01-22, 15 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7335.