Planning and build timeline
| Application submitted | 2012-01-20 |
| Permission granted | 2012-08-15 7 months after submission |
| Operational | 2016-10-03 50 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — Hertsmere
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tollgate Farm Battery Storage Battery · Under Construction | 49.5 | 1.7 km |
Aylett Nurseries - Solar Panels Solar Photovoltaics · Operational | — | 3.6 km |
Potters Bar Solar Farm Solar Photovoltaics · Operational | 5 | 4.1 km |
Land At Swanland Road Solar Photovoltaics · Operational | 5 | 4.1 km |
Blanche Lane, South Mimms - Solar Panels Solar Photovoltaics · Under Construction | 0.61 | 4.4 km |
Computacenter Warehouse Solar Photovoltaics · Under Construction | 2 | 5.3 km |
Elstree Film And TV Studios, Shenley Road - Solar Panels Solar Photovoltaics · Operational | 3 | 7.7 km |
Woodside Leisure Centre - Solar PV Panels Solar Photovoltaics · Operational | 0.29 | 10 km |
How big is Coursers Farm AD Plant (Waste AD)?
Coursers Farm AD Plant (Waste AD) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Coursers Farm AD Plant (Waste AD)?
REPD records the operator as Severn Trent (formerly Agrivert). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Coursers Farm AD Plant (Waste AD) approved and built?
The application was submitted on 2012-01-20. Permission was granted on 2012-08-15, 7 months later. The site became operational on 2016-10-03, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 370.