Novarly ParcelRenewable sites

Renewable sitesCoursers Farm AD Plant (Waste AD)

Coursers Farm AD Plant (Waste AD)

Coursers Farm AD Plant (Waste AD) is operational in Hertsmere with a recorded capacity of 3 MW, and has been generating since 2016-10-03.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-10-03
Anaerobic Digestion
Technology
Severn Trent (formerly Agrivert)
Hertsmere
Authority
England

Planning and build timeline

Application submitted2012-01-20
Permission granted2012-08-15
7 months after submission
Operational2016-10-03
50 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Tollgate Farm Battery Storage
Battery · Under Construction
49.51.7 km
Aylett Nurseries - Solar Panels
Solar Photovoltaics · Operational
3.6 km
Potters Bar Solar Farm
Solar Photovoltaics · Operational
54.1 km
Land At Swanland Road
Solar Photovoltaics · Operational
54.1 km
Blanche Lane, South Mimms - Solar Panels
Solar Photovoltaics · Under Construction
0.614.4 km
Computacenter Warehouse
Solar Photovoltaics · Under Construction
25.3 km
Elstree Film And TV Studios, Shenley Road - Solar Panels
Solar Photovoltaics · Operational
37.7 km
Woodside Leisure Centre - Solar PV Panels
Solar Photovoltaics · Operational
0.2910 km

How big is Coursers Farm AD Plant (Waste AD)?

Coursers Farm AD Plant (Waste AD) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Coursers Farm AD Plant (Waste AD)?

REPD records the operator as Severn Trent (formerly Agrivert). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Coursers Farm AD Plant (Waste AD) approved and built?

The application was submitted on 2012-01-20. Permission was granted on 2012-08-15, 7 months later. The site became operational on 2016-10-03, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 370.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council