Solar planning in Hertsmere

Hertsmere has decided 13 solar farms and approved 92% of them, taking a median of 1.8 months to decide. Consented capacity: 15 MW. 2 applications still awaiting a decision.

92%
Approved
12 granted · 1 refused
1.8 mo
Median decision
UK 2.3 mo
15 MW
Consented
1 MW refused
1
Appeals
0 allowed on appeal

How Hertsmere compares

Against the 298 UK authorities with 5+ solar decisions, Hertsmere sits in the 31st percentile for approval rate (1 points below the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2015)Refused — 1 (2015)215Approved — 1 (2016)116Approved — 3 (2022)322Approved — 3 (2023)323Approved — 1 (2024)124Approved — 2 (2025)225
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (17)

SchemeMWStatusDecided
David Lloyd Leisure Club, Hartspring Lane - Solar Panels
Unknown · 25/1015/PD56O · 1.6 mo to decide
0.28Awaiting Construction2025-09-02
Wrotham Park - Solar Panels
Enviromena · 25/1023/FUL
30Application Submitted2025-07-18
Centennial Park, Centennial Avenue - Solar Panels
Spire Healthcare Group PLC · 24/1652/PD56O · 2.3 mo to decide
0.17Awaiting Construction2025-02-25
North London Ad Plant, Coursers Road - Solar Panels
Severn Trent Green Power Group Limited · 24/0862/PD56O · 1.5 mo to decide
0.17Awaiting Construction2024-08-23
Hilfield - Solar arrays & Battery storage
Elstree Green Limited · 22/0948/FULEI
49.9Application Withdrawn2024-05-31
NIBSC, Blanche Lane - Solar Panels
MHRA · 23/1376/FUL · 1.8 mo to decide
0.22Awaiting Construction2023-12-07
Blanche Lane, South Mimms - Solar Panels
Private Developer · 22/0985/PD56O · 14.4 mo to decide
0.61Under Construction2023-08-23
Elstree Film And TV Studios, Shenley Road - Solar Panels And ASHPs
Hertsmere Borough Council · 23/0292/FUL
Application Withdrawn2023-05-03
Multi Storage, Cranborne Industrial Estate - Solar Panels
Multimessage Limited · 23/0384/PD56O · 1.6 mo to decide
0.16Awaiting Construction2023-04-26
Elstree Film And TV Studios, Shenley Road - Solar Panels
Sky Studios
3Operational2023-02-24
C P House, Otterspool Way - Solar Panels
CP Holdings Limited · 22/1736/PD56O · 1.8 mo to decide
0.28Awaiting Construction2022-12-07
Unit 2, York Crescent - Solar Panels
Panattoni UK Developments Limited · 22/1633/FUL · 1.6 mo to decide
0.22Awaiting Construction2022-11-22
Willows Activity Farm, Colney Heath - Solar Array
Cactus Energy · 22/0568/PD56O · 1.6 mo to decide
0.18Awaiting Construction2022-05-18
Hilfield Solar Farm & Battery Storage Facility
Elstree Green Limited · 21/0050/FULEI · 10.3 mo to decide
49.9Revised2021-11-19
Land At Swanland Road
Gascoyne Holdings · 15/0784/FUL · 7.4 mo to decide
5Operational2016-01-07
Potters Bar Solar Farm
UK Sustainable Energy · 15/1289/FUL · 3.5 mo to decide
5Operational2015-12-18
Bell Lane Solar Farm
Mulbrick Cleans Energy · 15/1287/FUL · 3 mo to decide
1Application Refused2015-11-26

Does Hertsmere approve solar farms?

Yes — of the 13 solar farms Hertsmere has decided, 92% were approved (12 granted, 1 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Hertsmere?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Hertsmere consented?

15 MW has been consented across 12 approved schemes, with 1 MW refused. A further 2 applications awaits a decision.

Other technologies in Hertsmere

Battery storage in HertsmereOnshore wind in Hertsmere

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.