Dagenham Docks Biogas (Waste AD)
Dagenham Docks Biogas (Waste AD) is operational in Barking and Dagenham with a recorded capacity of 1.4 MW, and has been generating since 2017-07-07.
Planning and build timeline
| Application submitted | 2013-08-01 |
| Permission granted | 2013-11-11 3 months after submission |
| Operational | 2017-07-07 44 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
East Dagenham Docks AD (AD) Anaerobic Digestion · Operational | 1.4 | 0.3 km |
Ford Motor Company Ltd (Extension) Wind Onshore · Operational | 2 | 1.1 km |
Ford Wind Park - Dagenham Wind Onshore · Operational | 5.9 | 1.2 km |
Crossness Sewage Works PV Solar Photovoltaics · Operational | 1.5 | 1.8 km |
Crossness Sewage Works Turbine Wind Onshore · Operational | 2.5 | 2.5 km |
Crossness Sewage Works Sewage Sludge Digestion · Operational | 5.7 | 2.5 km |
Riverside Resource Recovery Facility Battery Storage Battery · Under Construction | 2.5 | 2.5 km |
Twin Tumps Way - Solar Panels Solar Photovoltaics · Operational | 0.62 | 3.1 km |
How big is Dagenham Docks Biogas (Waste AD)?
Dagenham Docks Biogas (Waste AD) has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dagenham Docks Biogas (Waste AD)?
REPD records the operator as ReFood UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dagenham Docks Biogas (Waste AD) approved and built?
The application was submitted on 2013-08-01. Permission was granted on 2013-11-11, 3 months later. The site became operational on 2017-07-07, 44 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 328.