Novarly ParcelRenewable sites

Renewable sitesWraysbury Landfill

Wraysbury Landfill

Wraysbury Landfill is operational in Windsor and Maidenhead with a recorded capacity of 4.8 MW, and has been generating since 2017-03-21.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-21
Solar Photovoltaics
Technology
Sirius Solar Building
Windsor and Maidenhead
Authority
England

Planning and build timeline

Application submitted2014-07-02
Permission granted2014-10-29
4 months after submission
Operational2017-03-21
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Windsor and Maidenhead’s record on solar

Windsor and Maidenhead has decided 11 solar farms and approved 91%, taking a median of 1.8 months. See every solar farm decision in Windsor and Maidenhead

Other built sites within 15 km

SiteMWDistance
Norlands Lane Landfill Site
Landfill Gas · Operational
2.73.8 km
Norlands Lane Landfill Site (Extension)
Landfill Gas · Operational
44.5 km
Lakeside EfW
EfW Incineration · Operational
304.6 km
Colnbrook Landfill
Landfill Gas · Operational
1.94.7 km
Chertsey Water Treatment Works
Solar Photovoltaics · Operational
1.35.9 km
Heathrow Airport Biomass CHP
Biomass (dedicated) · Operational
1.86 km
Trumps Farm Landfill Scheme
Landfill Gas · Operational
2.97.3 km
Trumps Farm (AD)
Anaerobic Digestion · Operational
2.47.6 km

How big is Wraysbury Landfill?

Wraysbury Landfill has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wraysbury Landfill?

REPD records the operator as Sirius Solar Building. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wraysbury Landfill approved and built?

The application was submitted on 2014-07-02. Permission was granted on 2014-10-29, 4 months later. The site became operational on 2017-03-21, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1938.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council