Novarly ParcelRenewable sites

Renewable sitesHeathrow Airport Biomass CHP

Heathrow Airport Biomass CHP

Heathrow Airport Biomass CHP is operational in Hillingdon with a recorded capacity of 1.8 MW, and has been generating since 2013-01-01.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-01-01
Biomass (dedicated)
Technology
Heathrow Airport
Hillingdon
Authority
England

Planning and build timeline

Application submitted2010-03-02
Permission granted2010-05-25
3 months after submission
Operational2013-01-01
31 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Western International Market
Solar Photovoltaics · Operational
1.75.4 km
Western International Market (WIM) Site
Battery · Operational
0.25.4 km
Southall Lane Waste Depot
Battery · Operational
5.5 km
Lakeside EfW
EfW Incineration · Operational
305.5 km
Colnbrook Landfill
Landfill Gas · Operational
1.95.8 km
Wraysbury Landfill
Solar Photovoltaics · Operational
4.86 km
Charlton Lane Eco Park (ACT)
Advanced Conversion Technologies · Under Construction
3.66.2 km
Charlton Lane Eco Park (Waste AD)
Anaerobic Digestion · Operational
1.76.2 km

How big is Heathrow Airport Biomass CHP?

Heathrow Airport Biomass CHP has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Heathrow Airport Biomass CHP?

REPD records the operator as Heathrow Airport. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Heathrow Airport Biomass CHP approved and built?

The application was submitted on 2010-03-02. Permission was granted on 2010-05-25, 3 months later. The site became operational on 2013-01-01, 31 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 129.

Novarly Parcel · official public data, read properly · parcel.novarly.com