Renewable sitesNorlands Lane Landfill Site

Norlands Lane Landfill Site

Norlands Lane Landfill Site is operational in Runnymede with a recorded capacity of 2.7 MW, and has been generating since 1997-12-01.

2.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1997-12-01
Landfill Gas
Technology
Thames Waste Management
Runnymede
Authority
England

Planning and build timeline

Application submitted1997-03-11
Permission granted1997-06-10
3 months after submission
Operational1997-12-01
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Norlands Lane Landfill Site (Extension)
Landfill Gas · Operational
41 km
Chertsey Water Treatment Works
Solar Photovoltaics · Operational
1.32.5 km
Wraysbury Landfill
Solar Photovoltaics · Operational
4.83.8 km
Trumps Farm Landfill Scheme
Landfill Gas · Operational
2.94.6 km
Trumps Farm (AD)
Anaerobic Digestion · Operational
2.44.8 km
Charlton Lane Eco Park (ACT)
Advanced Conversion Technologies · Under Construction
3.66.2 km
Charlton Lane Eco Park (Waste AD)
Anaerobic Digestion · Operational
1.76.2 km
Heathrow Airport Biomass CHP
Biomass (dedicated) · Operational
1.86.8 km

How big is Norlands Lane Landfill Site?

Norlands Lane Landfill Site has a recorded installed capacity of 2.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Norlands Lane Landfill Site?

REPD records the operator as Thames Waste Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Norlands Lane Landfill Site approved and built?

The application was submitted on 1997-03-11. Permission was granted on 1997-06-10, 3 months later. The site became operational on 1997-12-01, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 597.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council