Lakeside EfW is operational in Slough with a recorded capacity of 30 MW, and has been generating since 2010-09-01.

30 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-09-01
EfW Incineration
Technology
Grundon Waste / Viridor
Slough
Authority
England

Planning and build timeline

Application submitted1999-08-06
Permission granted2000-03-26
8 months after submission
Operational2010-09-01
125 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Colnbrook Landfill
Landfill Gas · Operational
1.90.3 km
Wraysbury Landfill
Solar Photovoltaics · Operational
4.84.6 km
Heathrow Airport Biomass CHP
Biomass (dedicated) · Operational
1.85.5 km
Norlands Lane Landfill Site
Landfill Gas · Operational
2.78 km
Slough Sewage Treatment Works
Sewage Sludge Digestion · Operational
1.28.1 km
Slough Heat & Power Station
EfW Incineration · Under Construction
49.98.2 km
Western International Market (WIM) Site
Battery · Operational
0.28.2 km
Western International Market
Solar Photovoltaics · Operational
1.78.2 km

How big is Lakeside EfW?

Lakeside EfW has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lakeside EfW?

REPD records the operator as Grundon Waste / Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lakeside EfW approved and built?

The application was submitted on 1999-08-06. Permission was granted on 2000-03-26, 8 months later. The site became operational on 2010-09-01, 125 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 865.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council