Novarly ParcelRenewable sites

Renewable sitesTrumps Farm (AD)

Trumps Farm (AD)

Trumps Farm (AD) is operational in Runnymede with a recorded capacity of 2.4 MW, and has been generating since 2014-02-28.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-02-28
Anaerobic Digestion
Technology
Severn Trent (formerly Agrivert)
Runnymede
Authority
England

Planning and build timeline

Application submitted2010-09-15
Permission granted2011-05-12
8 months after submission
Operational2014-02-28
34 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Trumps Farm Landfill Scheme
Landfill Gas · Operational
2.90.4 km
Chertsey Water Treatment Works
Solar Photovoltaics · Operational
1.32.5 km
Norlands Lane Landfill Site
Landfill Gas · Operational
2.74.8 km
Norlands Lane Landfill Site (Extension)
Landfill Gas · Operational
45.2 km
Wraysbury Landfill
Solar Photovoltaics · Operational
4.87.6 km
Charlton Lane Eco Park (Waste AD)
Anaerobic Digestion · Operational
1.79.5 km
Charlton Lane Eco Park (ACT)
Advanced Conversion Technologies · Under Construction
3.69.5 km
Heathrow Airport Biomass CHP
Biomass (dedicated) · Operational
1.811.6 km

How big is Trumps Farm (AD)?

Trumps Farm (AD) has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trumps Farm (AD)?

REPD records the operator as Severn Trent (formerly Agrivert). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trumps Farm (AD) approved and built?

The application was submitted on 2010-09-15. Permission was granted on 2011-05-12, 8 months later. The site became operational on 2014-02-28, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 308.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council