Wormit Solar Farm

Wormit Solar Farm is operational in Fife with a recorded capacity of 4 MW, and has been generating since 2017-03-31.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-31
Solar Photovoltaics
Technology
Green Hedge (BayWa r.e.)
Fife
Authority
Scotland

Planning and build timeline

Application submitted2015-07-20
Permission granted2015-10-09
3 months after submission
Operational2017-03-31
18 months after consent

Fife’s record on solar

Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife

Other built sites within 15 km

SiteMWDistance
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array
Solar Photovoltaics · Under Construction
5.3 km
Eden Campus
Solar Photovoltaics · Operational
17.2 km
Sustainable Power and Research Campus
Biomass (dedicated) · Operational
6.57.2 km
Dunsinane Industrial Estate
Battery · Operational
49.97.8 km
Dundee Technology Park
Battery · Operational
49.98.4 km
Baldovie Industrial Estate (Forties Road)
EfW Incineration · Under Construction
108.5 km
Michelin Tyre Co Ltd - Dundee
Wind Onshore · Operational
48.7 km
Baldovie
EfW Incineration · Operational
8.38.7 km

How big is Wormit Solar Farm?

Wormit Solar Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wormit Solar Farm?

REPD records the operator as Green Hedge (BayWa r.e.). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wormit Solar Farm approved and built?

The application was submitted on 2015-07-20. Permission was granted on 2015-10-09, 3 months later. The site became operational on 2017-03-31, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5513.

Novarly Parcel · official public data, read properly · parcel.novarly.com