Baldovie Industrial Estate (Forties Road) is under construction in Dundee City with a recorded capacity of 10 MW.
Planning and build timeline
| Application submitted | 2016-12-22 |
| Permission granted | 2017-03-21 3 months after submission |
| Operational | not recorded |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Baldovie EfW Incineration · Operational | 8.3 | 0.2 km |
Michelin Tyre Co Ltd - Dundee Wind Onshore · Operational | 4 | 0.5 km |
Dunsinane Industrial Estate Battery · Operational | 49.9 | 6.8 km |
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array Solar Photovoltaics · Under Construction | — | 7.4 km |
Wormit Solar Farm Solar Photovoltaics · Operational | 4 | 8.5 km |
Dundee Technology Park Battery · Operational | 49.9 | 9.4 km |
Ark Hill Wind Onshore · Operational | 6.4 | 13.2 km |
Eden Campus Solar Photovoltaics · Operational | 1 | 13.3 km |
How big is Baldovie Industrial Estate (Forties Road)?
Baldovie Industrial Estate (Forties Road) has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Baldovie Industrial Estate (Forties Road)?
REPD records the operator as MVV Environment. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Baldovie Industrial Estate (Forties Road) approved and built?
The application was submitted on 2016-12-22. Permission was granted on 2017-03-21, 3 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6171.