Renewable sites › Eden Campus
Eden Campus
Eden Campus is operational in Fife with a recorded capacity of 1 MW, and has been generating since 2021-12-01.
Planning and build timeline
| Application submitted | 2019-11-18 |
| Permission granted | 2021-03-26 16 months after submission |
| Operational | 2021-12-01 8 months after consent |
Fife’s record on solar
Fife has decided 31 solar farms and approved 100%, taking a median of 3.7 months. See every solar farm decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sustainable Power and Research Campus Biomass (dedicated) · Operational | 6.5 | 0.1 km |
Wormit Solar Farm Solar Photovoltaics · Operational | 4 | 7.2 km |
Cupar Wastewater Treatment Works Solar Farm Solar Photovoltaics · Operational | 0.62 | 7.9 km |
Ferrymuir Battery · Under Construction | 49.9 | 11.2 km |
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array Solar Photovoltaics · Under Construction | — | 12.5 km |
Michelin Tyre Co Ltd - Dundee Wind Onshore · Operational | 4 | 13.2 km |
Baldovie Industrial Estate (Forties Road) EfW Incineration · Under Construction | 10 | 13.3 km |
Baldovie EfW Incineration · Operational | 8.3 | 13.5 km |
How big is Eden Campus?
Eden Campus has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Eden Campus?
REPD records the operator as Eden Campus Consultancy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Eden Campus approved and built?
The application was submitted on 2019-11-18. Permission was granted on 2021-03-26, 16 months later. The site became operational on 2021-12-01, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7531.
Novarly Parcel · official public data, read properly · parcel.novarly.com