Dundee Technology Park is operational in Dundee City with a recorded capacity of 49.9 MW, and has been generating since 2021-06-21.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-06-21
Battery
Technology
Gigabox Developments
Dundee City
Authority
Scotland

Planning and build timeline

Application submitted2020-04-30
Permission granted2020-10-09
5 months after submission
Operational2021-06-21
8 months after consent

Dundee City’s record on battery storage

Dundee City has decided 5 battery storage schemes and approved 80%, taking a median of 6 months. See every battery storage scheme decision in Dundee City

Other built sites within 15 km

SiteMWDistance
Dunsinane Industrial Estate
Battery · Operational
49.92.7 km
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array
Solar Photovoltaics · Under Construction
3.2 km
Wormit Solar Farm
Solar Photovoltaics · Operational
48.4 km
Baldovie
EfW Incineration · Operational
8.39.4 km
Baldovie Industrial Estate (Forties Road)
EfW Incineration · Under Construction
109.4 km
Michelin Tyre Co Ltd - Dundee
Wind Onshore · Operational
49.9 km
Ark Hill
Wind Onshore · Operational
6.411 km

How big is Dundee Technology Park?

Dundee Technology Park has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dundee Technology Park?

REPD records the operator as Gigabox Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dundee Technology Park approved and built?

The application was submitted on 2020-04-30. Permission was granted on 2020-10-09, 5 months later. The site became operational on 2021-06-21, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7946.