Wolverhampton EfW
Wolverhampton EfW is an operational 8 MW energy-from-waste plant in Wolverhampton, generating since 1 June 1998. Planning permission was granted on 11 April 1995, 4 months after submission. Operator of record: MES Environmental (CNIM Group).
Planning and build timeline
| Application submitted | 19 December 1994 |
| Permission granted | 11 April 1995 4 months after submission |
| Operational | 1 June 1998 38 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Wolverhampton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wolverhampton EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 6.9 | 2.1 km |
Solar Photovoltaics · Operational | 5.8 | 4.2 km |
Battery · Operational | 2 | 4.8 km |
Solar Photovoltaics · Operational | 5 | 5 km |
Battery · Operational | 4 | 5.5 km |
Battery · Operational | 41 | 7.8 km |
EfW Incineration · Under Construction | 49 | 7.9 km |
Solar Photovoltaics · Operational | 1.8 | 8 km |
How big is Wolverhampton EfW?
Wolverhampton EfW has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wolverhampton EfW?
REPD records the operator as MES Environmental (CNIM Group). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wolverhampton EfW approved and built?
The application was submitted on 19 December 1994. Permission was granted on 11 April 1995, 4 months later. The site became operational on 1 June 1998, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 814.