Renewable sites › Anchor Lane Energy Centre
Anchor Lane Energy Centre
Anchor Lane Energy Centre is an operational 4 MW battery storage site in Wolverhampton, generating since 1 October 2020. Planning permission was granted on 13 August 2021, 34 months after submission. Operator of record: Suncredit.
Planning and build timeline
| Application submitted | 19 October 2018 |
| Permission granted | 13 August 2021 34 months after submission |
| Operational | 1 October 2020 |
Screening a site of your own?
Redline runs the record on your own boundary in Wolverhampton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Anchor Lane Energy Centre’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 57 | 4 km |
EfW Incineration · Under Construction | 2 | 4.1 km |
Battery · Operational | 2 | 4.3 km |
Solar Photovoltaics · Under Construction | 6.9 | 4.5 km |
EfW Incineration · Operational | 8 | 5.5 km |
Landfill Gas · Operational | 4.4 | 5.7 km |
Advanced Conversion Technologies · Operational | 40 | 5.7 km |
EfW Incineration · Operational | 7.4 | 5.8 km |
How big is Anchor Lane Energy Centre?
Anchor Lane Energy Centre has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Anchor Lane Energy Centre?
REPD records the operator as Suncredit. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Anchor Lane Energy Centre approved and built?
The application was submitted on 19 October 2018. Permission was granted on 13 August 2021, 34 months later. The site became operational on 1 October 2020.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7156.