Jaguar Land Rover

Jaguar Land Rover is an operational 5.8 MW solar farm in South Staffordshire, generating since 31 March 2014. Planning permission was granted on 15 August 2014, 3 months after submission. Operator of record: Jaguar Land Rover.

5.8 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2014
Solar Photovoltaics
Technology
Jaguar Land Rover
South Staffordshire
Authority
England

Planning and build timeline

Application submitted15 May 2014
Permission granted15 August 2014
3 months after submission
Operational31 March 2014

Screening a site of your own?

RedlineUK · £39

South Staffordshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Jaguar Land Rover’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Staffordshire’s record on solar

South Staffordshire has decided 16 solar farms and approved 100%, taking a median of 2.8 months. See every solar farm decision in South Staffordshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.8 km
Solar Photovoltaics · Operational
1.84.1 km
EfW Incineration · Operational
84.2 km
EfW Incineration · Operational
234.8 km
Solar Photovoltaics · Under Construction
6.95.6 km
Battery · Operational
7.5 km
Solar Photovoltaics · Operational
15.87.5 km
Battery · Operational
27.8 km

How big is Jaguar Land Rover?

Jaguar Land Rover has a recorded installed capacity of 5.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Jaguar Land Rover?

REPD records the operator as Jaguar Land Rover. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Jaguar Land Rover approved and built?

The application was submitted on 15 May 2014. Permission was granted on 15 August 2014, 3 months later. The site became operational on 31 March 2014.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1491.