Novarly ParcelRenewable sites

Renewable sitesJaguar Land Rover

Jaguar Land Rover

Jaguar Land Rover is operational in South Staffordshire with a recorded capacity of 5.8 MW, and has been generating since 2014-03-31.

5.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
Jaguar Land Rover
South Staffordshire
Authority
England

Planning and build timeline

Application submitted2014-05-15
Permission granted2014-08-15
3 months after submission
Operational2014-03-31

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Staffordshire’s record on solar

South Staffordshire has decided 16 solar farms and approved 100%, taking a median of 2.8 months. See every solar farm decision in South Staffordshire

Other built sites within 15 km

SiteMWDistance
Land East of Lawn Lane
Solar Photovoltaics · Operational
50.8 km
Barr Farm
Solar Photovoltaics · Operational
1.84.1 km
Wolverhampton EfW
EfW Incineration · Operational
84.2 km
Four Ashes EfW
EfW Incineration · Operational
234.8 km
Bowmans Harbour Solar Farm
Solar Photovoltaics · Under Construction
6.95.6 km
Albrighton Solar farm
Solar Photovoltaics · Operational
15.87.5 km
Albrighton Solar farm
Battery · Operational
7.5 km
EPSRC Willenhall
Battery · Operational
27.8 km

How big is Jaguar Land Rover?

Jaguar Land Rover has a recorded installed capacity of 5.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Jaguar Land Rover?

REPD records the operator as Jaguar Land Rover. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Jaguar Land Rover approved and built?

The application was submitted on 2014-05-15. Permission was granted on 2014-08-15, 3 months later. The site became operational on 2014-03-31.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1491.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council