Renewable sites › Wolf Bog Wind Farm
Wolf Bog Wind Farm
Wolf Bog Wind Farm is operational in Mid and East Antrim with a recorded capacity of 8.8 MW, and has been generating since 2007-11-01.
Planning and build timeline
| Application submitted | 2004-05-01 |
| Permission granted | 2005-11-02 18 months after submission |
| Operational | 2007-11-01 24 months after consent |
Mid and East Antrim’s record on onshore wind
Mid and East Antrim has decided 21 onshore wind schemes and approved 81%, taking a median of 14.6 months. See every onshore wind scheme decision in Mid and East Antrim →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Corby Knowe Wind Onshore · Operational | 5 | 6.4 km |
Elliot's Hill Wind Farm Wind Onshore · Operational | 5 | 7.7 km |
Tully Quarry Anaerobic Digestion · Operational | 3 | 8.4 km |
The Michelin Tyre Factory - Ballymena Wind Onshore · Operational | 4.6 | 10.8 km |
Millar Farm Solar Photovoltaics · Operational | 6 | 12.3 km |
Ballymena Wind Park Limited Wind Onshore · Operational | 4.7 | 12.9 km |
Wind Turbine 1 Wind Onshore · Operational | 2.3 | 13.5 km |
Carn Hill Wind Onshore · Operational | 13.8 | 13.6 km |
How big is Wolf Bog Wind Farm?
Wolf Bog Wind Farm has a recorded installed capacity of 8.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wolf Bog Wind Farm?
REPD records the operator as B9 Energy / RES. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wolf Bog Wind Farm approved and built?
The application was submitted on 2004-05-01. Permission was granted on 2005-11-02, 18 months later. The site became operational on 2007-11-01, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3242.