Renewable sites › Millar Farm
Millar Farm
Millar Farm is an operational 6 MW solar farm in Antrim and Newtownabbey, generating since 27 March 2017. Planning permission was granted on 22 July 2015, 5 months after submission. Operator of record: Lightsource Renewable Energy.
Planning and build timeline
| Application submitted | 3 March 2015 |
| Permission granted | 22 July 2015 5 months after submission |
| Operational | 27 March 2017 20 months after consent |
Screening a site of your own?
Antrim and Newtownabbey approves 83% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Millar Farm’s recorded coordinate — swap in your own postcode or coordinates.
Antrim and Newtownabbey’s record on solar
Antrim and Newtownabbey has decided 12 solar farms and approved 83%, taking a median of 6.5 months. See every solar farm decision in Antrim and Newtownabbey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 1.7 | 5.2 km |
Solar Photovoltaics · Operational | 6.5 | 5.3 km |
Wind Onshore · Operational | 5 | 6.7 km |
Wind Onshore · Operational | 5 | 7.7 km |
Solar Photovoltaics · Operational | 4.8 | 8.3 km |
Anaerobic Digestion · Operational | 3 | 10.9 km |
Wind Onshore · Operational | 8.8 | 12.3 km |
Wind Onshore · Operational | 13.8 | 12.7 km |
How big is Millar Farm?
Millar Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Millar Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Millar Farm approved and built?
The application was submitted on 3 March 2015. Permission was granted on 22 July 2015, 5 months later. The site became operational on 27 March 2017, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5085.